Parkinson's Law |
Work expands to fill time available |
|
Ethnocentrism |
Viewpoint that ones group is the center of everything. Against which all other groups are judged |
|
Rolling wave planning |
Requires near term activities in greater detail and future activities at a higher level this is a form of progressive elaboration |
|
Crashing |
Technique used for schedule compression. Crashing refers to speeding up work by adding resources |
|
Crashing |
Technique used for schedule compression. Crashing refers to speeding up work by adding resources |
|
Fast tracking |
Schedule compression technique. Refers to executing multiple activities in parallel to speed up project work |
|
Scope |
The sum of the products, services and results to be provided as a project |
|
WBS |
Back (Definition) |
|
Project time management |
The activities included processes required to manage and ensure the timely completion of the project accomplished by activities that are sequenced |
|
Schedule method - critical path |
Sequence of activities that define shortest duration and longest path |
|
Schedule method - critical path |
Sequence of activities that define shortest duration and longest path |
|
Schedule method - critical chain |
Account for limited resources using buffers on tasks |
|
Schedule model |
Mock up or representation of schedule |
|
Six sigma quality |
sets a very high standard of quality |
|
Total quality management |
Continuous quality improvement --> applies improvements in process and project results --> people focused with goal of continually increasing customer satisfaction |
|
PDCA |
Plan do check act - created Walter shewart perfected by demming |
|
PDCA |
Plan do check act - created Walter shewart perfected by demming |