Time Management processes
|
Define Activities
Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule Control Schedule |
|
Define Activities Inputs
|
Scope Baseline
Enterprise environmental factors Organizational process assets |
|
Define Activities Tools & Techniques
|
Decomposition
Rolling wave planning Templates Expert judgment |
|
Define Activities Outputs
|
Activity list
Activity attributes Milestone list |
|
Sequence Activities Inputs
|
Activity list
Activity attributes Milestone list Project scope statement Organizational process assets |
|
Sequence Activities Tools & Techniques
|
Precedence diagramming method (PDM)
Dependency determination Applying leads and lags Schedule network templates |
|
Sequence Activities Outputs
|
Project schedule network diagrams
Project document updates |
|
Estimate Activity Resources Inputs
|
Activity list
Activity attributes Resource calendars Enterprise environmental factors Organizational process assets |
|
Estimate Activity Resources Tools & Techniques
|
Expert judgment
Alternative analysis Published estimating data Bottom-up estimating Project management software |
|
Estimate Activity Resources Outputs
|
Activity resource requirements
Resource breakdown structure Project document updates |
|
Estimate Activity Durations Inputs
|
Activity list
Activity attributes Activity resource requirements Resource calendars Project scope statement Enterprise environmental factors Organizational process assets |
|
Estimate Activity Durations Tools & Techniques
|
Expert judgment
Analogous estimting Parametric estimating Three-point estimates Reserve analysis |
|
Estimate Activity Durations Outputs
|
Activity duration estimates
Project document updates |
|
Develop Schedule Inputs
|
Activity list
Activity attributes Project schedule network diagrams Activity resource requirements Resource calendars Activity duration estimates Project scope statement Enterprise environmental factors Organizational process assets |
|
Develop Schedule Tools & Techniques
|
Schedule network analysis
Critical path method Critical chain method Resource leveling What-if scenairo analysis Applying leads and lags Schedule compression Scheduling tool |
|
Develop Schedule Outputs
|
Project schedule
Schedle baseline Schedule data Project document updates |
|
Control Schedule Inputs
|
Project management plan
Project schedule Work performance information Organizational process assets |
|
Control Schedule Tools & Techniques
|
Performance reviews
Variance analysis Project management software Resource leveling What-if scenairo analysis Adjusting leads and lags Schedule compression Scheduling tool |
|
Control Schedule Outputs
|
Work performance measurements
Organizational process assets updates Change requests Project management plan updates Project document updates |
|
Schedule Variance (SV)
|
SV = EV – PV
|
|
Schedule Performance Index (SPI)
|
SPI – EV/PV
|
|
Cost Variance (CV)
|
CV = EV-AC
|
|
Cost Performance Index (CPI)
|
CPI = EV/AC
|
|
Estimate at Completion (EAC) Steady Rate
|
EAC = BAC/CPI
|
|
Estimate at Completion (EAC) performing at the Budget Rate
|
EAC = AC + (BAC - EV)
|
|
Estimate at Completion (EAC) IF considering schedule & cost performance
|
EAC = AC + (BAC-EV)/(CPI * SPI)
|
|
Estimate to Complete (ETC)
|
ETC = (BAC-EV)/CPI
|
|
To-Complete Performance Index (TCPI) Based on the BAC
|
TCPI = (BAC-EV)/(BAC-AC)
|
|
To-Complete Performance Index (TCPI) Based on the EAC
|
TCPI = (BAC-EV)/(EAC-AC)
|
|
Variance At Completion
|
VAC = BAC – EAC
|