• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/8

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

8 Cards in this Set

  • Front
  • Back

No. of Communication Channels

n (n-1)/2


n= number of members in the team

Scheduled Performance Index (SPI)

SPI= EV/ PV



PV= Planned Value


EV= Earned Value



<1 behind schedule


=1 on schedule


> 1 ahead of schedule

Cost Performance Index (CPI)

CPI= EV/AC



EV= Earned Value


AC= Actual Cost



<1 over budget


=1 on budget


>1 under budget

Schedule Variance (SV)

SV = EV – PV



EV = Earned Value


PV = Planned Value



< 0 Behind schedule


= 0 On schedule


> 0 Ahead of schedule


Cost Variance (CV)

CV = EV – AC



EV = Earned Value


AC = Actual Cost



< 0 Over budget


= 0 On budget


> 0 Within budget


Estimate to Completion (ETC)

ETC= EAC- AC



EAC= Estimate at Completion


AC= Actual Cost

Variance at Completion (VAC)

VAC= BAC - EAC



BAC= Budget at Completion


EAC = Estimate at Completion



<0 under budget


=0 on budget


>0 over budget

PERT Estimation

(O + 4M + P)/ 6



O= Optimistic Estimate


M= Most Likely Estimate


P= Pessimistic Estimate