8 Cards in this Set
- Front
- Back
No. of Communication Channels |
n (n-1)/2 n= number of members in the team |
|
Scheduled Performance Index (SPI) |
SPI= EV/ PV
PV= Planned Value EV= Earned Value
<1 behind schedule =1 on schedule > 1 ahead of schedule |
|
Cost Performance Index (CPI) |
CPI= EV/AC
EV= Earned Value AC= Actual Cost
<1 over budget =1 on budget >1 under budget |
|
Schedule Variance (SV) |
SV = EV – PV
EV = Earned Value PV = Planned Value
< 0 Behind schedule = 0 On schedule > 0 Ahead of schedule
|
|
Cost Variance (CV) |
CV = EV – AC
EV = Earned Value AC = Actual Cost
< 0 Over budget = 0 On budget > 0 Within budget
|
|
Estimate to Completion (ETC) |
ETC= EAC- AC
EAC= Estimate at Completion AC= Actual Cost |
|
Variance at Completion (VAC) |
VAC= BAC - EAC
BAC= Budget at Completion EAC = Estimate at Completion
<0 under budget =0 on budget >0 over budget |
|
PERT Estimation |
(O + 4M + P)/ 6
O= Optimistic Estimate M= Most Likely Estimate P= Pessimistic Estimate |