The Planning Process Group encompasses which knowledge management areas?
|
All. Integration, Scope, Time, Cost, Quality, Human Resource, Communications, Risk, and Procurement Management knowledge areas.
|
|
How many processes are there within the Planning Process Group?
|
20.
|
|
What process(es) is/are within the Planning Process Group and Integration Management knowledge area?
|
Develop Project Management Plan.
|
|
What process(es) is/are within the Planning Process Group and Scope Management knowledge area?
|
Collect Requirements, Define Scope, and Create Work Breakdown Structure.
|
|
What process(es) is/are within the Planning Process Group and Time Management knowledge area?
|
Define Activities, Sequence Activities, Estimate Activity Resources, Estimate Activity Durations, and Develop Schedule.
|
|
What process(es) is/are within the Planning Process Group and Cost Management knowledge area?
|
Estimate Costs and Determine Budget.
|
|
What process(es) is/are within the Planning Process Group and Quality Management knowledge area?
|
Plan Quality.
|
|
What process(es) is/are within the Planning Process Group and Human Resource Management knowledge area?
|
Develop Human Resource Plan.
|
|
What process(es) is/are within the Planning Process Group and Communication Management knowledge area?
|
Plan Communications.
|
|
What process(es) is/are within the Planning Process Group and Risk Management knowledge area?
|
Plan Risk Management, Identify Risks, Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis, and Plan Risk Responses.
|
|
What process(es) is/are within the Planning Process Group and Procurement Management knowledge area?
|
Plan Procurements.
|
|
What is Develop Project Management Plan?
|
Is the process that creates an important document that guides the project's execution and control.
|
|
What is the Project Management Plan?
|
Also known as the project plan, it is the plan on how the project will be managed.
|
|
Characterize the Project Management Plan.
|
A formal, approved document composed of the other planning documents.
|
|
What are the inputs to the Develop Project Management Plan process?
|
The project charter and other planning outputs that make up the components of the Project Management Plan.
|
|
The project charter is an output of which process?
|
Develop Project Charter.
|
|
What tool(s) or technique(s) are used in the Develop Project Management Plan process?
|
Expert Judgement.
|
|
What is/are the output(s) of the Develop Project Management Plan process?
|
The Project Management Plan.
|
|
Is the Project Management Plan a formal, written piece of communication?
|
Yes.
|
|
Is the Project Management Plan a single document or thirteen separate plans?
|
A single document made up of thirteen separate plans when they are approved as the project plan.
|
|
Who approves the Project Management Plan?
|
Depending on the organizational structure, it is usually the project manager, sponsor, and functional managers providing resources.
|
|
For the PMP exam, should you consider the Project Management Plan as being detailed or being a summary document?
|
Detailed.
|
|
Name the component(s) of the Project Management Plan that is/are created in the Develop Project Management Plan process.
|
Change, Configuration, Scope, Schedule, and Cost Management Plans.
|
|
Name the component(s) of the Project Management Plan that is/are created in the Plan Quality process.
|
Quality Management Plan and Process Improvement Plan.
|
|
Name the component(s) of the Project Management Plan that is/are created in the Develop Human Resource Plan process.
|
Human Resources Plan.
|
|
Name the component(s) of the Project Management Plan that is/are created in the Plan Communications Plan process.
|
Communications Management Plan.
|
|
Name the component(s) of the Project Management Plan that is/are created in the Plan Risk Management process.
|
Risk Management Plan.
|
|
Name the component(s) of the Project Management Plan that is/are created in the Plan Procurements process.
|
Procurement Management Plan.
|
|
Name the component(s) of the Project Management Plan that is/are created in the Collect Requirements process.
|
Requirements Management Plan.
|
|
Name the component(s) of the Project Management Plan that is/are created in the Create WBS process.
|
Scope Baseline.
|
|
Name the component(s) of the Project Management Plan that is/are created in the Determine Budget process.
|
Cost Performance Baseline.
|
|
Name the component(s) of the Project Management Plan that is/are created in the Develop Schedule process.
|
Schedule Baseline.
|
|
What is the correct sequence for the following activities?
- Create work breakdown structure - Create project scope structure - Create activity list |
Create project scope structure, Create work breakdown structure, Create activity list.
|