• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/20

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

20 Cards in this Set

  • Front
  • Back
BCWP
Budgeted Cost of Work Performed or Earned Value
Earned Value
BCWP
BCWS
Planned Value
Planned value
BCWS
ACWP
Actual Cost
Actual Cost
ACWP
Cost Spending Variance
BCWP - ACWP
+ means under budget
Schedule Varience
BCWP-BCWS
+ means ahead of schedule
CPI
Cost Performance Index
BCWP/ACWP
<1, over budget
SPI
Scheduled Performance Index
BCWP/BCWS
<1, behind schedule
BCWP
Budgeted Cost of Work Performed or Earned Value
Earned Value
BCWP
BCWS
Planned Value
Planned value
BCWS
ACWP
Actual Cost
Actual Cost
ACWP
Cost Spending Variance
BCWP - ACWP
+ means under budget
Schedule Varience
BCWP-BCWS
+ means ahead of schedule
CPI
Cost Performance Index
BCWP/ACWP
<1, over budget
SPI
Scheduled Performance Index
BCWP/BCWS
<1, behind schedule