Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
19 Cards in this Set
- Front
- Back
“Generally, but not always, the sequence of schedule activities that determines the duration of the project. Its is the longest path through the project”
|
Critical Path
|
|
original approved project schedule
|
Schedule Baseline
|
|
Used to analyze variances between actual and planned schedule performance
|
Schedule Baseline
|
|
Longest Path through the project
|
Critical Path
|
|
“The process of developing and approximation of the monetary resources needed to complete project activities”
|
Estimate Costs
|
|
“involves aggregating the estimates costs of individual activities work packages to establish a cost baseline.”
|
Determine Budget Process
|
|
Benefits of Life Cycle Costing
|
Awareness of total costs
Cost reduction by comparing alternatives Forecasts future resource needs Supports strategic planning and budgeting |
|
“Any form of schedule network analysis in which scheduling decisions (start and finish dates) are driven by resource constraints (e.g., limited resource availability or difficult – to manage changes in resource availability levels).
|
Resource Leveling
|
|
Limitations of Life Cycle Costing
|
Limited accuracy
Inappropriate for smaller projects Sensitivity to changing requirements |
|
Life Cycle Costing Purpose
|
Total direct and indirect costs
Recurring and non-recurring costs Related costs estimated to be incurred over the life of a project and its product* |
|
True or False
Resource Leveling can result in changing the finish date of a project |
True
|
|
Resource Leveling Techniques (Under the Leveling topic)
|
Identify resource peaks
Delay non-critical tasks with float Review estimates Extend schedule if needed* Decompose activities further into smaller tasks |
|
The path in a schedule network that takes the longest time to complete:
|
Critical Path
|
|
True or False
Technical Performance Measurement is a technique that attempts to move activities to a new point in the schedule so the resources are not over utilized. |
False
Resource Leveling |
|
Including all costs associated with a project over its entire life is know as:
|
Life Cycle Costing
|
|
Resource leveling will often affect the project schedule by making it:
|
Longer
|
|
What is the name of the original approved project schedule:
|
Schedule Baseline
|
|
An activity’s scheduled flexibility is know as:
|
Float
|
|
Name 2 types of float
|
Total Float
Free Float |