• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/25

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

25 Cards in this Set

  • Front
  • Back
Earned Value Measurement (EVM)
To perform calculations gather measurements of PV, AC, and EV. Performed on work packages and control accounts of the WBS.
Planned Value (PV)
Percent complete where the project should be. Established during the Planning processes.
PV = number of days projected for a task / its budgeted cost.
Earned Value (EV)
Percent complete x budget at completion.
Actual Cost (AC)
Actual cost of completing the work component in a given time period.
Cost Variance (CV)
CV = EV - AC
Schedule Variance (SV)
SV = EV - PV
Performance Indexes
Used to calculate performance efficiencies.
Cost Performance Index (CPI)
CPI = EV / AC
Schedule Performance Index (SPI)
SPI = EV / PV
To-Complete Performance Index BAC
BAC = (BAC - EV) / (BAC - AC)
To-Complete Performance Index EAC
EAC = (BAC - EV) / (EAC - AC)
Variance at Completion (VAC)
VAC = BAC - EAC
Estimate at Completion (EAC)
EAC = AC + ETC
Estimate to Complete (ETC)
ETC = EAC - AC
PERT: Expected Value
(optimistic + pessimistic + (4 x most likely)) / 6
Critical Path Method (CPM)
Calculating the Forward pass, Backward pass, and Float
Forward Pass
Working from left to right it gives you early start and early finish.
Backward Pass
Start from the finish and work your way to the start. Gives you late finish and late start.
Float
Subtract early start from late start, or early finish from late finish.
Cost Estimating
Base the estimate on work effort.
Bottom-Up Estimating
Start at the work package level of WBS and calculate the cost of each activity assigned to that work package. Sum of all work package estimates provides the estimate of the total project cost. Last piece of data needed is the rate for each resource.
Analogous Estimating (Top-down estimating)
Approximates the cost of the project at a high level by a similar past project as a basis for the estimate, along with expert judgment. Used during the business case development or during the early stages of scope planning when there isn't a lot of detail. Not used to estimate individual work packages.
Parametric Estimating
Computes costs by multiplying the quantity of work by the rate. Used on complex projects or within specialized industries.
Risk Impacting
Calculate a final risk score for each of the risks on your list.
Present Value
i = interest rate
n = number of time periods
PV = (FV/((1 + i)^n))