Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/16

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

16 Cards in this Set

  • Front
  • Back
What is the 1 Initiating Process from the Planning Group?
Develop Project Managment Plan
What are the Inputs & Outputs of "Develop Project Management Plan"?
Inputs-
Project Charter
Outputs from other Planning Process groups
EEF
OPA

Outputs
Project Management Plan
What are the components of the Project Management Plan?
Change MP
Configuration MP
Scope MP
Schedule MP
Cost MP
Schedule Baseline
Cost Performance Baseline
Scope Baseline
HR Plan
Quality MP
Process Improvement Plan
Communications MP
Risk MP
Procurement MP
Requirements MP
What are the 3 Scope Planning Processes?
Collect Requirements
Define Scope
Create WBS
What are the Inputs & Outputs of "Collect Requirements" Process?
Inputs
Project Charter
Stakholder Register

Outputs
Requirements Documents
Requirments Management Plan
Requirements Traceabilty Matrix
What are the Inputs & Outputs of the "Define Scope" process?
Inputs
Requirements Documentation
Project Charter
OPA

Outputs
Project Scope Statement
What are the Inputs & Outputs of "Create WBS"?
Inputs
Project Scope Statement
Requirements Documentation
OPA

Outputs
Scope baseline
-WBS/WBS Dictionary
PDU
What are the 5 Planning Processes of the Time Knowledge Group?
Define Activities
Sequence Activities
Estimate Activity Resources
Estimate Activity Duration
Develop Schedule
What are the Imputs and Outputs of "Define Activities"?
Inputs
Scope Baseline
EEF
OPA

Outputs
Activity List
Activitiy Attributes
Milestone List
What are the Imputs and Outputs of "Sequence Activities"?
Inputs
Activity List
Activity Attributes List
Project Scope Statement
OPA

Outputs
Project Network Schedule
PDU's
What are the Inputs and Outputs of "Esitmate Activity Resources"?
Activity List
Activity Attributes
Resource Calendar
EEF
OPA

Outputs
Activity Resource Estimates
What are the Inputs and Output of the "Estimate Cost" process?
Inputs
Scope Baseline
Project Schedule
HR Plan
Risk Register
EEF
OPA

Outputs
Activity Cost Estimates
Basis of Estimates
PDU's
What are the Inputs and Outputs of "Estimate Activity Durations"?
Inputs
Activity List
Activity Attributes
Acitivity Resoruce Estimates
Resoruce Calendar
project Scope Statement

Output
Activity Duration Estimates
What are the Imputs and Outputs of "Determine Budget"?
Inputs
Scope baseline
Activity Cost Estimates
Basis of Estimates
Project Schedule
Resource Calendar
Contract
OPA

Outputs
Project Funding Requirements
cost Performance Baseline
PDU's
What are the 2 Processes from the Cost Knowldege Group in the Planning Process?
Estimate Cost
Develop Budget
What are the Inputs and Outputs of "Develop Schedule"?
Inputs
Activity List
Activity Attributes
Project Scope Statement
Project Network Schedule
Activity Resource Estimates
Resource Calendar
Activity Duration Estimates
EEF
OPA

Outputs
Project Schedule
Schedule Data
Schedule Baseline
PDU's