Which of the following is not true of obtaining project plan approval?
|
c. only one person needs to approve the project management plan and that's the project manager
|
|
Joe is a project manager. Uses ishikawa diagrams to come for root cause.
|
B. perform quality assurance
|
|
Which of the following shows roles and responsibilites on your project?1
|
`c. Raci matrix
|
|
Brandi is is a project manager on a software project. About halfway through development her team found that they had not estimated enough time for some of the technical work they needed to do.
|
a. update the scope and schedule baselines to reflect the approved change
|
|
Your project has a virtual team. Half of your team members are located in another country, where they are working for a subcontractor. You want to promote the top performing foreign team member to a leadership position.
|
a. inform the subcontractor that they must adopt a non discriminator policy or you will be forced to terminate the contract and find a subcontractor that does not discriminate against women
|
|
Which of the following is not a source of information about specific project constraints and assumptions?
|
a. the project scope management plan.
|
|
When do you perform stakeholder analysis?
|
a, when defining the project scope
|
|
A team member approaches you with a change that could cut your schedule down by a month. What is the first thing you should do?
|
c. figure out the impact on the scope of the owrk and the cost before you write up the change request.
|
|
When are the most expensive defects most likely to be introduced into a product?
|
b. when the product is being designed
|
|
You are the project manager for a railroad construction project. Your sponser has asked you for a forecast for the cost projection. the project has a total budget of $80000
|
a. 59210
|