Where is the best location for leveling a crane?
|
Upperworks
|
|
When determining the a gross load the best method is:
|
Get an accurate load weight and add the rigging.
|
|
By order of hitch strength, which is the correct answer?
|
Basket, vertical, choker
|
|
What is the purpose of using a Jib?
|
To increase height
|
|
When taking a side strain on a boom, what concerns the operator most?
|
Boom damage
|
|
You should always have at least how many wraps on a hoist drum?
|
2
|
|
On a load chart, values above the bold line mean:
|
Capacities based on structural competence.
|
|
The primary purpose for a rooster sheave or Auxiliary boom point sheave is to:
|
Separate the hoist lines.
|
|
What is the proper procedure when using an insulating link or a boot near power lines?
|
Be sure to maintain the correct allowable distance from the lines. OSHA
|
|
When the number of layers of rope on a drum increases the:
|
Allowable line pull decreases
|
|
What is the minimum allowable distance from the crane and powerlines under 50kV?
|
10 ft.
|
|
The term Upperworks or Superstructure refer to the area of the crane:
|
above the turntable
|
|
Side loading my be cause by:
|
Starting or stopping the swing to rapidly.
|
|
What is the best procedure to follow when underground utilities may be present?
|
Contact local utility company
|
|
Eccentric main boom tip reeving causes:
|
Twisting of the boom
|
|
How many randomly broken wires must there be to remove a running wire rope from service?
|
6 OSHA and ANSI
|
|
When lifting personnel in a man basket using 6 X 19 wire rope, the minimum safety factor is?
|
7 OSHA and ANSI
|
|
What is the safety factor required when using non-rotating wire rope and lifting personnel in a man basket?
|
10 OSHA
|
|
Who has the responsibility for determining the correct weight of a load?
|
Supervisor
|
|
When working near powerlines when is a signal person required?
|
When crane moves within a booms length of the powerline
|
|
When an operator leaves the crane, he must first:
|
Put the load on the ground and put all dogs or pawls in.
|
|
If replacing the hoist line wire rope on a crane, how do you determine the size or type of
wire rope to use? |
Use Manufacturer’s operator’s manual or load chart
|
|
After the crane has been checked out and before crane lift operations begin the crew should:
|
Have a pre-lift meeting OSHA (g)(8)
|
|
According to ANSI B30.5 personnel platform lifts should not be made with wind in excess of:
|
15 mph ANSI 5-3.2.2(21)
|
|
When is it safe to work closer than the allowable distance from powerlines?
|
When utility company says lines are de-energized OSHA
|
|
During setup how do you determine machine clearances (counterweight, boom, outrigger)?
|
Measure for correct distances
|
|
When operating a crawler crane what is the most unstable allowable quadrant of operation?
|
Side
|
|
When operating a truck crane what is the most unstable allowable quadrant of operation?
|
Side
|
|
What is not a good location for crane setup?
1. Compacted fill 2. Hard fill 3. Above utilities 4. Concrete |
Above utilities
|
|
When should a tagline be used?
|
When rotation of load would be dangerous ANSI 5-3.2.1.4(o)
|
|
When an operator arrives at the jobsite and the crane is already erected, how would the operator check the main and auxiliary hoist brakes?
|
Lift the load off the ground and apply the brake ANSI 5-3.2.1.4(g)
|
|
What is the difference between an Anti-two-block warning device and an Anti-two-block prevention system?
|
Warning device only warns, but prevention system will stop the operation
|
|
Who gives the operator hand signals?
|
The person assigned prior to the lift
|
|
Why use mats or cribbing?
|
To reduce ground pressure
|
|
Tipping capacities of crawler cranes are based on what percentage of tipping?
|
75%
|
|
Should the load be applied when determining the proper boom angle?
|
Yes Charts
|
|
When should the operator use the run by the seat of the pants technique?
|
Never
|
|
Load radius is the distance from the center of gravity of the suspended load to the:
|
Center of rotation IPT, Charts
|
|
What is the primary reason for using a boom extension?
|
Increase Height
|
|
What is the minimum design factor required for a right regular lay main, boom or auxiliary hoist rope?
|
3.5
|
|
When telescoping the boom section of an R/T, which section should be telescoped first?
|
All sections should be telescoped equally Charts
|
|
How does the operator determine if correct load chart is being used?
|
Matching Serial number
|
|
Net capacity is equal to:
|
Gross capacity minus capacity deductions
|
|
If the SWL of a cranes wire rope is 10,000 lbs using one part, what is the SWL when using 4 parts?
|
40,000 lbs.
|
|
When first arriving on the jobsite, the operator should first determine the condition of the:
|
Access Roads
|
|
How does the operator verify the LMIs boom length or load radius reading?
|
Actual Measurements
|
|
If the rated capacity of the crane is above the solid line or within the shaded areas or has an asterisk next to it, this means the capacity is based on:
|
Structural competence
|
|
All hazards and potential problems should be discovered during the:
|
Pre-lift site inspection
|
|
How many broken wires must be present in one strand of one lay for running wire rope to be removed from service?
|
3
|
|
In a range diagram, boom length and angle can be used to determine:
|
Load radius
|