Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
15 Cards in this Set
- Front
- Back
Testing of completed systems shall be performed as required by the technical specifications of the |
contract. |
|
Contractor Punch-Out: Near the completion of all work or any increment thereof, the contractor prepares a |
punch list and makes corrections. |
|
The contractor should correct deficiencies promptly so that project schedules are |
met. |
|
All major deficiencies noted during this contractor's punch-out inspection must be corrected prior to the |
pre-final inspection. |
|
Pre-Final and Final Inspections: Participating in the pre-final and final inspections will be |
QA personnel and QC personnel |
|
Any deficiencies noted at these inspections by client/customer personnel will be examined by the Government and the contractor notified if corrective action is |
required |
|
Complete As-Built Drawings: As-built drawings are updated continually |
throughout the project. |
|
While the status of as- built drawings is a concern throughout the project, it is of particular significance, as the project comes to an end, |
to prevent any loose ends. |
|
Operations and Maintenance (O&M) Manuals: The QC Manager will assure submittal of all required operation and maintenance data in accordance with |
scheduled submittal dates. |
|
Instruction and Training Procedures: If the contract requires operation and maintenance training of client/customer personnel, the QC Manager will make certain all specified training has been conducted by |
qualified instructors. |
|
Materials Turnover: The QC Manager will verify that all required keys, spare parts and materials have been sorted, identified, and demonstrated to be |
usable prior to final inspection. |
|
Warranty: The QC Manager will ensure that all warranty information |
is provided. |
|
FAR Clause 52.246-21 Warranty of Construction, states the general warranty period for construction work is one year from the time of |
acceptance by the government . |
|
If the manufacturers of individual components provide a longer warranty, this extended warranty period accrues to |
the government |
|
If the contractor repairs or replaces a component of the project during the warranty period then this component is warranted for |
one year from the repair or replacement date. |