Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
28 Cards in this Set
- Front
- Back
Contract clause, "Specifications and Drawings for Construction," requires the contractor to review |
plans and specifications and request clarification where necessary. |
|
The term "Request for Information (RFI)" and other similar terms are often used to ask for clarification of the |
contract |
|
CQC personnel shall review site |
conditions and restraints: |
|
CQC personnel shall review proper allowance for |
maintenance space and access: |
|
CQC personnel shall review Conflicts and discrepancies between |
plans and specifications |
|
RFI Process: The contractor should include procedures in the QC plan for an |
RFI process. |
|
Each RFI may be handled by separate |
letter, by pre-printed forms, or on the daily QC report, as mutually agreed |
|
The RFI questions should be |
specific and clearly presented |
|
The RFI answers should be documented |
as mutually agreed |
|
When the contractor notes a discrepancy, a recommended solution should be included with the |
RFI. |
|
When a subcontractor or supplier submits a RFI, the prime contractor has to |
review the request and coordinate it among his offices and with other firms. |
|
For design-build contracts the designer of record must answer RFI’s concerning the |
contractor's design and extensions of design required by the plans and specifications. |
|
The QC Manager must review contractor furnished |
designs |
|
Design-Build: In this type of contract, the contractor's QC efforts must include |
design quality control |
|
Design-Build: The QC plan must include details of reviews to be implemented to ensure that the design will |
comply with the criteria provided |
|
Extensions of Design: Many contracts contain requirements for the contractor to provide designs such as |
pre-engineered metal buildings, fire alarm and protection systems, cathodic protection, etc |
|
Extensions of Design: It becomes critical that the contractor designs are coordinated with all other aspects of the project so that proper |
interfaces are maintained |
|
Extensions of Design: Where required (structural steel details, concrete reinforcement drawings, etc.) by the contractor, subcontractors, or suppliers they must be coordinated with other |
activities. |
|
Value Engineering Change Proposal (VECP): is based on a
|
partnering philosophy |
|
Value Engineering Change Proposal (VECP): recognizes that the Government and the contractor share common goals and that, by working together in a spirit of cooperation, we can produce a |
quality facility while saving the taxpayer money. |
|
Value Engineering Change Proposal (VECP): After acceptance of the VECP, the QC Manager must ensure that changes are discussed in the |
control meetings. |
|
Design-Build: The QC Manager must be in place for the design phase of design-build contracts and must take an |
active role |
|
Design-Build: The QC Manager must review constructability, operability, environmental, review of all |
drawings and specifications, |
|
Design-Build: The QC Manager must coordinate between the different disciplines and trades to prevent any |
interferences. |
|
Name three instances of contractor extensions of designs. |
a |
|
Name some possible areas that must be addressed during the contractor's coordination review of plans and specifications |
a |
|
What are the responsibilities of the QC Manager during the design phase of a design-build project? |
a |
|
Under no circumstance should the RFI be passed to the Government without |
QC Managers coordination being accomplished. |