• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/45

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

45 Cards in this Set

  • Front
  • Back
The CHAOS studies found the average cost overrun
ranged from 180 percent in 1994 to 56 percent in 2004; other studies found overruns to be 33-34 percent
What is Cost and Project Cost Management? Cost
is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange
What is Cost and Project Cost Management? Management
includes the processes required to ensure that the project is completed within an approved budget
Project Cost Management Processes: Estimating
developing an approximation or estimate of the costs of the resources needed to complete a project
Project Cost Management Processes: Determine Budget
allocating the overall cost estimate to individual work items to establish a baseline for measuring performance
Project Cost Management Processes: Controlling costs
controlling changes to the project budget
Basic Principles of Cost Management: Tangible costs
or benefits are those costs or benefits that an organization can easily measure in dollars
Basic Principles of Cost Management: Intangible Costs
or benefits are costs or benefits that are difficult to measure in monetary terms
Basic Principles of Cost Management: Direct Costs
are costs that can be directly related to producing the products and services of the project
Basic Principles of Cost Management: Indirect Costs
are costs that are not directly related to the products or services of the project, but are indirectly related to performing the project
Basic Principles of Cost Management: Sunk cost
is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs
Learning curve theory states
that when many items are produced repetitively, the unit cost of those items decreases in a regular pattern as more units are produced
Reserves are
dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict
Contingency reserves allow for
future situations that may be partially planned for (sometimes called known unknowns) and are included in the project cost baseline
Management reserves
allow for future situations that are unpredictable (sometimes called unknown unknowns)
When Estimating Costs
Project managers must take cost estimates seriously if they want to complete projects within budget constraints
When Estimating Costs
It’s important to know the types of cost estimates, how to prepare cost estimates, and typical problems associated with IT cost estimates
A cost management plan is
a document that describes how the organization will manage cost variances on the project
Basic tools and techniques for cost estimates: Analogous or top-down estimates:
use the actual cost of a previous, similar project as the basis for estimating the cost of the current project
Basic tools and techniques for cost estimates: Bottom-up estimates:
involve estimating individual work items or activities and summing them to get a project total
Basic tools and techniques for cost estimates: Parametric modeling
uses project characteristics (parameters) in a mathematical model to estimate project costs
Typical Problems with IT Cost Estimates
Estimates are done too quickly
Cost budgeting involves
allocating the project cost estimate to individual work items over time
The WBS is a required input to the cost budgeting process since
it defines the work items
Important goal is to produce a cost baseline
A time-phased budget that project managers use to measure and monitor cost performance
Project cost control includes:
Monitoring cost performance
EVM is
a project performance measurement technique that integrates scope, time, and cost data
Given a baseline (original plan plus approved changes), you can
determine how well the project is meeting its goals
Earned Value Management Terms: Planned Value (PV)
formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period
Earned Value Management Terms: Actual Cost (AC)
formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period
Earned Value Management Terms: Earned Value (EV)
formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed
EV is based on
the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to date
Rate of performance (RP) is
the ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity
Rules of Thumb for Earned Value Numbers: Negative numbers
for cost and schedule variance indicate problems in those areas
Rules of Thumb for Earned Value Numbers: CPI and SPI less
than 100% indicate problems
Rules of Thumb for Earned Value Numbers: Problems mean
the project is costing more than planned (over budget) or taking longer than planned (behind schedule)
Rules of Thumb for Earned Value Numbers: The CPI can be used to calculate the estimate at completion (EAC),
an estimate of what it will cost to complete the project based on performance to date; the budget at completion (BAC) is the original total budget for the project
Five levels for project portfolio management
Put all your projects in one database
Earned Value (EV)
EV = PV to date * RP
Cost Variance (CV)
CV = EV - AC
Schedule Variance (SV)
SV = EV - PV
Cost Performace Index (CPI)
CPI = EV / AC
Schedule Performance Index (SPI)
SPI = EV / PV
Estimate at completion EAC
EAC = BAC / CPI
Estimates time to complete
Original time / SPI