Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
45 Cards in this Set
- Front
- Back
The CHAOS studies found the average cost overrun
|
ranged from 180 percent in 1994 to 56 percent in 2004; other studies found overruns to be 33-34 percent
|
|
What is Cost and Project Cost Management? Cost
|
is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange
|
|
What is Cost and Project Cost Management? Management
|
includes the processes required to ensure that the project is completed within an approved budget
|
|
Project Cost Management Processes: Estimating
|
developing an approximation or estimate of the costs of the resources needed to complete a project
|
|
Project Cost Management Processes: Determine Budget
|
allocating the overall cost estimate to individual work items to establish a baseline for measuring performance
|
|
Project Cost Management Processes: Controlling costs
|
controlling changes to the project budget
|
|
Basic Principles of Cost Management: Tangible costs
|
or benefits are those costs or benefits that an organization can easily measure in dollars
|
|
Basic Principles of Cost Management: Intangible Costs
|
or benefits are costs or benefits that are difficult to measure in monetary terms
|
|
Basic Principles of Cost Management: Direct Costs
|
are costs that can be directly related to producing the products and services of the project
|
|
Basic Principles of Cost Management: Indirect Costs
|
are costs that are not directly related to the products or services of the project, but are indirectly related to performing the project
|
|
Basic Principles of Cost Management: Sunk cost
|
is money that has been spent in the past; when deciding what projects to invest in or continue, you should not include sunk costs
|
|
Learning curve theory states
|
that when many items are produced repetitively, the unit cost of those items decreases in a regular pattern as more units are produced
|
|
Reserves are
|
dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict
|
|
Contingency reserves allow for
|
future situations that may be partially planned for (sometimes called known unknowns) and are included in the project cost baseline
|
|
Management reserves
|
allow for future situations that are unpredictable (sometimes called unknown unknowns)
|
|
When Estimating Costs
|
Project managers must take cost estimates seriously if they want to complete projects within budget constraints
|
|
When Estimating Costs
|
It’s important to know the types of cost estimates, how to prepare cost estimates, and typical problems associated with IT cost estimates
|
|
A cost management plan is
|
a document that describes how the organization will manage cost variances on the project
|
|
Basic tools and techniques for cost estimates: Analogous or top-down estimates:
|
use the actual cost of a previous, similar project as the basis for estimating the cost of the current project
|
|
Basic tools and techniques for cost estimates: Bottom-up estimates:
|
involve estimating individual work items or activities and summing them to get a project total
|
|
Basic tools and techniques for cost estimates: Parametric modeling
|
uses project characteristics (parameters) in a mathematical model to estimate project costs
|
|
Typical Problems with IT Cost Estimates
|
Estimates are done too quickly
|
|
Cost budgeting involves
|
allocating the project cost estimate to individual work items over time
|
|
The WBS is a required input to the cost budgeting process since
|
it defines the work items
|
|
Important goal is to produce a cost baseline
|
A time-phased budget that project managers use to measure and monitor cost performance
|
|
Project cost control includes:
|
Monitoring cost performance
|
|
EVM is
|
a project performance measurement technique that integrates scope, time, and cost data
|
|
Given a baseline (original plan plus approved changes), you can
|
determine how well the project is meeting its goals
|
|
Earned Value Management Terms: Planned Value (PV)
|
formerly called the budgeted cost of work scheduled (BCWS), also called the budget, is that portion of the approved total cost estimate planned to be spent on an activity during a given period
|
|
Earned Value Management Terms: Actual Cost (AC)
|
formerly called actual cost of work performed (ACWP), is the total of direct and indirect costs incurred in accomplishing work on an activity during a given period
|
|
Earned Value Management Terms: Earned Value (EV)
|
formerly called the budgeted cost of work performed (BCWP), is an estimate of the value of the physical work actually completed
|
|
EV is based on
|
the original planned costs for the project or activity and the rate at which the team is completing work on the project or activity to date
|
|
Rate of performance (RP) is
|
the ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity
|
|
Rules of Thumb for Earned Value Numbers: Negative numbers
|
for cost and schedule variance indicate problems in those areas
|
|
Rules of Thumb for Earned Value Numbers: CPI and SPI less
|
than 100% indicate problems
|
|
Rules of Thumb for Earned Value Numbers: Problems mean
|
the project is costing more than planned (over budget) or taking longer than planned (behind schedule)
|
|
Rules of Thumb for Earned Value Numbers: The CPI can be used to calculate the estimate at completion (EAC),
|
an estimate of what it will cost to complete the project based on performance to date; the budget at completion (BAC) is the original total budget for the project
|
|
Five levels for project portfolio management
|
Put all your projects in one database
|
|
Earned Value (EV)
|
EV = PV to date * RP
|
|
Cost Variance (CV)
|
CV = EV - AC
|
|
Schedule Variance (SV)
|
SV = EV - PV
|
|
Cost Performace Index (CPI)
|
CPI = EV / AC
|
|
Schedule Performance Index (SPI)
|
SPI = EV / PV
|
|
Estimate at completion EAC
|
EAC = BAC / CPI
|
|
Estimates time to complete
|
Original time / SPI
|