• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/6

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

6 Cards in this Set

  • Front
  • Back

How do you conduct a fee proposal?

Resource schedule gives a cost. Expressed as percentage of contract sum, hourly rate, lump sum.


What are the main elements included in a fee proposal?

Terms and conditions
Scope of services
Exclusions
Assumptions – e.g. programme

If you put together a fee proposal, but a couple of months into the job you realise that you have under forecasted your resources, would you go back to the client and ask for more money?

If project requirements (services, scope, value) have increased, then would go back to client for more fees
But if remained the same, it is a mistake so deal with it and get it right next time.
Do not reduce level of service you offered originally.

Once you and your client agreed the services to be provided verbally what would you do next?

Follow up with a letter which included terms and conditions, fee and scope of services in writing.

If the client gives you a lump sum fee before going on holiday, what would you do?


Place in a separately identified client account and agree a drawdown of monies against services.

If a client was prepared to pay you in advance for services you were providing, how would you ensure this was dealt with?

Set up a separate named and clearly identifiable client account.
Provide the client with a statement of account.
Inform and agree drawdowns.
Prior to drawing monies send an updated statement with how much and for what fees
Once complete, show a final statement, ensure everything is complete and transparent.