How many Prerequisites and Credits does EA have? |
4 Prerequisites and 7 optional credits. |
|
what are EA pre-requisites & optional Credits? |
P1) Fundamental commissioning & verification C1) Enhanced Commissioning . P2) Minimum Energy Performance. C2) Optimize Energy Performance P3) Bldg level Energy metering C3) Advance Energy metering P4) Fundamental Refrigerant Management C6) Enhanced Refrigerant Management C4) Demand Response C5) Renewable Energy Production C7) Green Power and Carbon Offsets |
|
What is Intent of EA P1 Fundamental of Cx & Verification? |
Support design, construction, and eventual operation of a project to meet OPR for energy, water, IEQ and durability. |
|
In concept process OPR is prepared, what is OPR? |
Owner's Project Requirements is a written document detailing the functional requirements of a project and the expectations of the building's use and operation. Prepared during the Integrative Process by owner or CxA with owner's direct input. |
|
What are the typical systems that are Commissioned? |
HVAC, Electric, Plumbing, Onsite renewable energy, Building envelope (acknowledge in doc but implementation not required) |
|
What is BOD? |
The Basis of design describes the systems to be commissioned and outline any design assumptions that are otherwise included in the design documents. How project meet the OPR. Prepared during the Schematic Design or Design development phase, OPR is consulted. |
|
What are the standard references for EA P1? |
ASHRAE Guideline 0-2005 ASHRAE Guideline 1.1-2007 for HVAC & R NIBS Guideline 3-2012 for Exterior Enclosures |
|
What are the Requirements of EA PR1 that CxA must do? |
- Review OPR, BOD and design - Develop & implement Cx Plan - Confirm Cx req. included in construction doc - Develop Const. Checklist - Develop system test Procedures - Verify System test execution - Maintain an issues log throughout Cx process. - Prepare final Cx process report - Doc all findings & recommendations and report directly to the owner. |
|
Cx Authority pre-qualification |
- Min experience of 2 buildings in Cx - Independent of the design & Const. teams - Project Less than 20,000 sq.ft the CxA may be from design or Const. team. |
|
what is operation and maintenance plan? |
Technical manual describing how the facilities manager can operate the bldg efficiently. Prepared by CxA, with help from team. |
|
What O&M Plan includes? |
- Sequence of operations - Occupancy schedule - Equipment run-time schedule - setpoints for all HVAC equipment - Set lighting levels - min Outside air requirements - schedule or setpoint changes - Elec & Mech system narratives - Preventive maintenance plan - Cx program |
|
When CxA to do the design review. |
Prior to 50% construction document phase. |
|
Steps for the Implementation of Cx Process |
1- Designate CxA, 2- Establish OPR & BOD 3- CxA review OPR & BOD 4- Develope & Implement Cx Plan 5- Cx req. added to const. documents 6- Develop Const. Checklists 7- Develop a system text procedure 8- Verify system test execution 9- Maintain a log of issues & benefits 10- Complete a summary Cx report |