• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/13

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

13 Cards in this Set

  • Front
  • Back

How many Prerequisites and Credits does EA have?

4 Prerequisites and 7 optional credits.

what are EA pre-requisites & optional Credits?

P1) Fundamental commissioning & verification


C1) Enhanced Commissioning .


P2) Minimum Energy Performance.


C2) Optimize Energy Performance


P3) Bldg level Energy metering


C3) Advance Energy metering


P4) Fundamental Refrigerant Management


C6) Enhanced Refrigerant Management


C4) Demand Response


C5) Renewable Energy Production


C7) Green Power and Carbon Offsets

What is Intent of EA P1 Fundamental of Cx & Verification?

Support design, construction, and eventual operation of a project to meet OPR for energy, water, IEQ and durability.

In concept process OPR is prepared, what is OPR?

Owner's Project Requirements is a written document detailing the functional requirements of a project and the expectations of the building's use and operation.




Prepared during the Integrative Process by owner or CxA with owner's direct input.

What are the typical systems that are Commissioned?

HVAC, Electric, Plumbing, Onsite renewable energy,


Building envelope (acknowledge in doc but implementation not required)

What is BOD?

The Basis of design describes the systems to be commissioned and outline any design assumptions that are otherwise included in the design documents. How project meet the OPR.




Prepared during the Schematic Design or Design development phase, OPR is consulted.

What are the standard references for EA P1?

ASHRAE Guideline 0-2005


ASHRAE Guideline 1.1-2007 for HVAC & R




NIBS Guideline 3-2012 for Exterior Enclosures

What are the Requirements of EA PR1 that CxA must do?

- Review OPR, BOD and design


- Develop & implement Cx Plan


- Confirm Cx req. included in construction doc


- Develop Const. Checklist


- Develop system test Procedures


- Verify System test execution


- Maintain an issues log throughout Cx process.


- Prepare final Cx process report


- Doc all findings & recommendations and report directly to the owner.

Cx Authority pre-qualification

- Min experience of 2 buildings in Cx


- Independent of the design & Const. teams




- Project Less than 20,000 sq.ft the CxA may be from design or Const. team.

what is operation and maintenance plan?

Technical manual describing how the facilities manager can operate the bldg efficiently.




Prepared by CxA, with help from team.

What O&M Plan includes?

- Sequence of operations


- Occupancy schedule


- Equipment run-time schedule


- setpoints for all HVAC equipment


- Set lighting levels


- min Outside air requirements


- schedule or setpoint changes


- Elec & Mech system narratives


- Preventive maintenance plan


- Cx program

When CxA to do the design review.

Prior to 50% construction document phase.

Steps for the Implementation of Cx Process

1- Designate CxA,


2- Establish OPR & BOD


3- CxA review OPR & BOD


4- Develope & Implement Cx Plan


5- Cx req. added to const. documents


6- Develop Const. Checklists


7- Develop a system text procedure


8- Verify system test execution


9- Maintain a log of issues & benefits


10- Complete a summary Cx report