Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
52 Cards in this Set
- Front
- Back
What is the goal of an indexing technique?
|
to reflect how a cost has changed
|
|
Are entry and exit criteria utilized for phases?
|
yes
|
|
What does a To-Complete Performance Index (TCPI) 20% higher or lower than the Cost Performance Index (CPI) indicate?
|
Estimate At Completion (EAC) not indicative of past performance
|
|
What might serve as the first clue that a project needs to be killed?
|
variances
|
|
Which is more time-intensive, bottom-up or top-down estimating?
|
bottom-up
|
|
To which component of a project plan is a WBS attached?
|
to the Scheduled Tasks
|
|
What 'fudge factor' should be added to time estimates if you are a skilled PM but the team is not experienced?
|
1.5 - 2x
|
|
Who should be the first to know if a project loses an important resource?
|
the sponsor
|
|
What 'fudge factor' should be added to time estimates when neither the PM nor the team are experienced?
|
3x
|
|
What is another term for earned value?
|
Budgeted Cost of Work Performed (BCWP)
|
|
What percentage should be added to time estimates to account for quality control?
|
10-25%
|
|
The parametric technique is a blend of which two techniques?
|
linear regression and unit
|
|
What percentage should be added to time estimates to account for overhead?
|
25%
|
|
What does To-Complete Performance Index measure?
|
efficiency
|
|
What is the formula for the To-Complete Performance Index (TCPI)?
|
work remaining (BAC-BCWP) / funds remaining (BAC-ACWP)
|
|
What is the process of breaking deliverables and requirements down into their component parts called?
|
decomposition
|
|
What factor does the unit technique require?
|
a per-unit cost
|
|
What is a cost driver?
|
any entity that has a direct relationship with a cost
|
|
What can be used to deal with team members who don't like each other?
|
team building
|
|
Does an SOW show costs?
|
no, only tasks to be performed
|
|
When would a PERT chart be used, as opposed to a Gantt?
|
when the project is large or complex
|
|
What is linear regression used for?
|
comparing the relationship between two variables
|
|
What is a simple, effective method of beginning rough decomposition?
|
sticky notes
|
|
Are entry and exit criteria used for tasks?
|
no
|
|
What two cost estimating techniques map one data element to another?
|
linear regression and parametric
|
|
Who should a possible scope change be communicated to first?
|
the sponsor
|
|
What is a status date?
|
the date when a measurement will be taken on how much has been spent on a task
|
|
Who signs the final project plan?
|
the sponsor
|
|
What is 'crashing a project'?
|
concentrating lots of people on a specific area to bring a deliverable in quickly
|
|
Why should SOW's be included in WBS's?
|
because they can affect dependencies
|
|
Which section of a project plan describes philosophical or political situations, technological climate, strategic attitudes, etc.?
|
Environmental Issues
|
|
When presented with a top-down budget, which constraint is most likely to be compromised?
|
quality
|
|
What is the Budgeted Cost of Work Performed?
|
the estimate of how much the completed tasks should have cost
|
|
What component is at the beginning of a project plan?
|
the table of contents
|
|
What is the Budget At Completion (BAC)?
|
the budgeted cost of the entire project
|
|
What are the two most likely causes of budget overruns?
|
too much time spent on a task and an item that costs more than expected
|
|
What is the chief constraint in a top-down budget?
|
the budget
|
|
What team group is responsible for overall architectural control?
|
the technical group
|
|
What is the budgeted cost of work scheduled?
|
How much it should have cost to complete the work that was scheduled
|
|
What is the Estimate At Completion (EAC)?
|
the current estimate of cost at completion
|
|
What is an iterative process?
|
one that is done over and over
|
|
Does a positive variance indicate you are over or under budget?
|
under
|
|
What two things are required in order to proceed with a WBS?
|
sign-off by sponsor and consensus among stakeholders
|
|
When you discover a team member working on something out of scope, what are your two options?
|
put the item through change control or cancel item
|
|
What is the formula for Schedule Variance (SV)?
|
BCWP - BCWS
|
|
What is the formula for Cost Variance (CV)?
|
BCWP - ACWP
|
|
What is a baseline?
|
an estimated schedule before work begins
|
|
What is unit testing?
|
testing of each individual component of a project
|
|
What is a variance?
|
the difference between the actual and budgeted values
|
|
What is the formula for Cost Performance Index (CPI)?
|
BCWP / ACWP
|
|
What is a 'push'?
|
any effort to speed creation of a deliverable
|
|
What is the formula for Schedule Performance Index (SPI)?
|
BCWP / BCWS
|