12 Cards in this Set

  • Front
  • Back
What is Project Closeout? What does that entail?
- the process of completing a construction project. this includes:
- contractual requirements
- approvals
- financial resolution
- required documentation
- post project evaluation
Project closeout is not easy to coordinate. What things need to be done?
1. Completion of seemingly minor details of work.
2. Delivery of late material and equipment.
3. Replacement of defective materials, equipment, or parts of assemblies.
4. Repair of defective workmanship.
5. Testing and approval of building systems and processes.
What is a punch list? Who prepares this list?
- A list of items to be completed prior to acceptance
Prepared by:
- contractor
- owner
- architect/engineer
- subcontractor
What is substantial completion?
The point in the project when the architect has determined that the facility or a portion of it is acceptable for owner use and occupancy. aka Beneficial Occupancy
Why is the date of substantial completion so important?
The date of substantial completion is extremely important because it stops the potential of liquidated damages.
List 4 essential elements of an SCC (Substantial Completion Certificate).
- Project ID
- Date of issuance/SC
- Description of the project or portion of the project
- list of remaining responsibilites
- Definition of "Substantial Completion"
- Signatures
- List of agreements
What does CCC stand for?
Construction Completion Certificate
What does FAC stand for?
Final Acceptance Certificate
How are a Construction Completion Certificate and Final Acceptance Certificate different?
Maintenance period begins and ends. For CCC, contractor assumes repair costs. For an FAC, the City assumes all maintenance.
Contracts need to provide what sort of paperwork upon project closeout?
Lien releases, written waranties, operating and maintenance manuals.
How must a contractor go about preparing record or "as-built" drawings?
- record actual dimensions,
- location of utilities
- any changes in drawing
What does an "affidavit of payment" certify?
An "affidavit of payment" certifies that payment of all debts and claims relating to the project has been made.