• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/19

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

19 Cards in this Set

  • Front
  • Back
What should happen before an owner pays a contractor?
The owner's inspector or representative reviews the payment request.
True or False?
Longer jobs are often paid out in one comprehensive payment.
False. Longer jobs often involve progress payments (i.e. monthly)
What are progress payments?
Partial payments for work completed during a portion of a construction period.
True or False?
Unit-price payments are found more frequently in public works contracts.
True
True or False?
Lump-sum payments often require that the inspector keep a daily tally of materials used or labor performed.
False, this is true of Unit-Price payments
When making progress payments, what one thing must the inspector be certain about?
That all items for which the contractor has claimed payment have been completed.
Unit prices often include costs for...?
Supply and Install
Most contracts deduct an amount for this from the amount earned during that period.
Retainage
What is retainage?
The amount held by the owner until the final completion of the contract.
Give two reasons why most contracts will use retainage in their progress payments.
1) Gives the owner the resources to complete the project, in case of a breach.
2) Covers material supplier and subcontractor liens on the project
True or False?
When making progress payments, materials don't include those that are delivered to the jobsite.
False.
Materials can include those that are stored away from the jobsite, in progress payments.
True.
What is the owner's primary concern with materials and progress payments?
Stored materials are in fact incorporated into the projects.
True or False?
In most cases, progress payments are legally comparable to advances.
True.
True or False?
In most cases, payments legally signify acceptance of work.
False.
What are three types of earthen materials pay quantities?
1) Bank cubic meter
2) Loose cubic meter
3) Compacted cubic meter
Why use pay quantities for earthen materials?
A given mass of soil material will occupy different volumes depending on its state of compaction.
True or False?
The owner may reject the schedule of values submitted and request a revision by the contractor.
True
What are some reasons why an owner may reject the schedule of values?
- excessive front-loading: a common method of allocating overhead and profit
- insufficient detail of construction activities
- noncompliance with contract requirements