What is a "dummy" in terms of the critical path method of scheduling?
|
Dummy - an activity used to show the graphical relationship on a CPM network
- used as a logical connector but which does not represent an actual work item |
|
What is an early start?
|
The earliest time at which an activity can be started
|
|
What is a late start?
|
The latest time an activity can be started without lengthening the project.
|
|
What is an early finish?
|
The earliest time at which an activity can be completed
|
|
What is a late finish?
|
The latest time an activity can be finished without lengthening the project.
|
|
What is a finish float?
|
An activity float which identifies the amount of time an activity start can be delayed without delaying the late finish of any following activity.
|
|
What is a total float?
|
Activity float which identifies the amount of time an activity start can be delayed without delaying the overall completion date of the project.
|
|
What are the 3 objectives of scheduling?
|
To determine:
- how (method of completion) - when (time to complete) - who/what (resources/costs) in order to complete any project. |
|
What are 4 types of schedules?
|
- Bar or Gantt Charts
- Progress or S Curves - Matrix - Critical Path Network |