9 Cards in this Set

  • Front
  • Back
What is a "dummy" in terms of the critical path method of scheduling?
Dummy - an activity used to show the graphical relationship on a CPM network
- used as a logical connector but which does not represent an actual work item
What is an early start?
The earliest time at which an activity can be started
What is a late start?
The latest time an activity can be started without lengthening the project.
What is an early finish?
The earliest time at which an activity can be completed
What is a late finish?
The latest time an activity can be finished without lengthening the project.
What is a finish float?
An activity float which identifies the amount of time an activity start can be delayed without delaying the late finish of any following activity.
What is a total float?
Activity float which identifies the amount of time an activity start can be delayed without delaying the overall completion date of the project.
What are the 3 objectives of scheduling?
To determine:
- how (method of completion)
- when (time to complete)
- who/what (resources/costs)
in order to complete any project.
What are 4 types of schedules?
- Bar or Gantt Charts
- Progress or S Curves
- Matrix
- Critical Path Network