Earned Value (EV)=
|
Percent Complete X Planned Value (PV)
|
|
Cost Performance Index
|
(CPI) = EV/AC
|
|
Schedule Performance Index
|
(SPI)= EV/PV
|
|
Schedule Variance
|
(SC) = EV-PV
|
|
Estimate at Completion
|
(EAC)= BAC/CPI
|
|
Estimate to Complete
|
(ETC) = EAC-AC
|
|
Variance at Completion
|
(VAC)= BAC-EAC
|
|
To Complete Performance Index
|
(TCPI)= (BAC-EV)/(BAC-AC)
|
|
PERT
|
(P+O+(4*R))/6
|
|
VARIANCE
|
((P-O)/6)SQUARED
|
|
Stand Dev
|
(P-O)/6
|
|
3 Point Est
|
(P+O+R)/3
|
|
Point of Total Assumption (PTA)
|
(Ceiling Price - Target Price)
--------------- + Target Cost Buyer Share |