• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/11

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

11 Cards in this Set

  • Front
  • Back
Planned Value (PV)
The physical work scheduled, plus the authorized budget to accomplish the scheduled work
Formerly known as budgeted cost of work scheduled (BCWS)
What the project should be worth at this point in the schedule
Cost Variance (CV)
EV - AC
+ve good
- ve bad
Schedule Variance (SV)
EV - PV
+ve good
-ve bad
Cost Performance Index (CPI)
EV/AC
>1 good
<1 bad
Schedule Performance Index (SPI)
EV/PV
>1 good
<1 bad
Cost Variance Percentage (CV%)
CV/EV
+ve good
-ve bad
Schedule Variance Percentage (SV%)
SV/PV
+ve good
-ve bad
Earned Value (EV)
% Complete x BAC

formerly budgeted cost of work performed (BCWP)
Estimate at Completion (EAC)
BAC/CPI
<BAC good
>BAC bad
Variance at Completion (VAC)
BAC - EAC
+ve good
-ve bad
Estimate to Completion (ETC)
EAC - AC
N/A good and bad