Culvert design is what percent of total road costs? |
5-10 |
|
Define peak flow |
The max volume of H20 in a river over time period |
|
How is peak flow described |
-in terms of rainfall event frequency |
|
Q2 is |
Mean annual flow |
|
Q 100 is |
100 year return peak flow |
|
Q is |
Volume passing through cross section of creek or culvert in m^3/sec |
|
Q depends on (7) (PRTGSDD) |
-previous weather conditions -rain -topography -ground cover -soil/subsoil -drainage area -drainage pattern |
|
Culvert capacity depends on (2) |
-shape and area of inlet - depth of h20 (H; headwater pool) at inlet |
|
H value Mof allows (2) |
-1 -0.7 - 0.8 normal |