Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
23 Cards in this Set
- Front
- Back
A critical path activity will generally have ho much float?
|
Zero.
|
|
What is the earned value name for "how much have spent to date?"
|
actual cost
|
|
What is a management reserve?
|
Amount of ime or money set aside to cover unforseen risks.
|
|
What is the formula for total float?
|
LS-ES or LF-EF. The amount of time a project can be delayed without delaying the project.
|
|
What are sunk costs?
|
Expended costs
|
|
What is the duration of a milestone?
|
Zero.
|
|
What does a benefit cost ratio of 2.5 mean?
|
The benefits are 2 1/2 times the cost. (Not a math problem)
|
|
The "what-if" scenario mehtod of schedule network analysis primarily makes use of what technique?
|
Monte Carlo analysis.
|
|
What schedule network analysis technique involves crashing?
|
Schedule compression.
|
|
Why would a project manager want to use resource leveling?
|
To smooth the peaks and vallyes of monthly resources usage consumed by the project.
|
|
What is value analysis?
|
Finding a less costly way to complete work without affecting quality.
|
|
What schedule network analysis technique uses buffers?
|
Critical chain
|
|
What does a milestone chart show?
|
Dates of significant events on the project.
|
|
Cost risk is greater for the buyer in what type of contract?
|
Cost reimbursable.
|
|
What is parametric estimating?
|
Using mathematical relationships found in historical information to create estimates.
|
|
What is the critical path?
|
The longest duration path in the networks; the shortest time to complete the project.
|
|
What is the range of accuracy with a definitive estimate?
|
+/- 10%
|
|
What does present value mean?
|
The value today of future cash flows.
|
|
What is analogous estimating?
|
Top-down estimating.
|
|
What are direct cost?
|
Costs incurred directly by the project.
|
|
Why would you crash a project?
|
To shorten the project duration.
|
|
What estimating method would use optimistic time estimates?
|
Three-points estimate.
|
|
What are fixed costs?
|
Costs that do not change with project activity.
|