• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/14

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

14 Cards in this Set

  • Front
  • Back
Four elements we need to know for almost any EVM calculation.
PV, EV, AC, BAC
Another name for PV.
BCWS
Another name for EV.
BDWP
The nine possible project states.
(Think of matrix)
Over bud, behind sched
Over bud, on sched
Over bud, ahead sched
On bud, behind sched
On bud, on sched
On bud, ahead sched
Under bud, behind sched
Under bud, on sched
Under bud, ahead sched
What is always first data element in an EVM formula?
EV
SV =
EV-PV
SPI =
EV/PV
CV =
EV-AC
CPI =
EV/AC
A phrase for SPI
"over/behind schedule"
A phrase for CPI
"over/behind budget"
EAC (most basic formula) =
BAC/CPI
RTD =
DAC/SPI
What is DAC (verbal)?
Originally intended project duration (Duration At Completion).