Four elements we need to know for almost any EVM calculation.
|
PV, EV, AC, BAC
|
|
Another name for PV.
|
BCWS
|
|
Another name for EV.
|
BDWP
|
|
The nine possible project states.
|
(Think of matrix)
Over bud, behind sched Over bud, on sched Over bud, ahead sched On bud, behind sched On bud, on sched On bud, ahead sched Under bud, behind sched Under bud, on sched Under bud, ahead sched |
|
What is always first data element in an EVM formula?
|
EV
|
|
SV =
|
EV-PV
|
|
SPI =
|
EV/PV
|
|
CV =
|
EV-AC
|
|
CPI =
|
EV/AC
|
|
A phrase for SPI
|
"over/behind schedule"
|
|
A phrase for CPI
|
"over/behind budget"
|
|
EAC (most basic formula) =
|
BAC/CPI
|
|
RTD =
|
DAC/SPI
|
|
What is DAC (verbal)?
|
Originally intended project duration (Duration At Completion).
|