• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/20

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

20 Cards in this Set

  • Front
  • Back

It is important that ____ understand all aspects of crane setup, site prep and site evaluation

Crane operators

The process that attempts to ID hazards and devise plans to overcome or eliminate all hazards which may interfere with crane operations is reflected in the ______

Site analysis

When in doubt of the surroundings at a crane site it is wise to consult with the ____ about the exact location of possible hazards

Local utility company

During transport and setup the ____ of a crane can break through the ground and cause damage

wheels/crawlers

When a signal person raps on his or her hard hat with their fist you should ______

Use the main hoist

Pinch point clearance ensures that no one will be inadvertently trapped or crushed and that ______

clearance is provided for the crane as the lift is being conducted

What will happen if the crane is not setup within 1% of level

Crane stability will be negatively impacted

Standby cranes must be inspected at least ___

Semiannually

When load rotation may be hazardous a ____ should be used

tag line

During lift operations what is the minimum clearance from overhead power lines rated at 60,000 volts

15 ft

The minimum clearance from overhead power lines rated at 345,000 volts for a crane in transit ___ feet

16

T/F Copies of load charts for crane operations can be obtained from OSHA

False

Measures and displays the weight of the load being hoisted

load indicator

Uses solenoid operated blocking and bypass valves

selected controls lockout system

Measures how far the boom is extended

boom length sensor

The travel distance on hand levers may not be more than ____ inches from neutral position on a two way lever

14

The force on hand levers may not be more than ____ pounds

35

No crane should be operated with a load that exceeds _____

the limits on load charts

Verifying the load weight and capacity of the crane is the responsibility of _____

the crane operator

When the crane is shutdown the boom should be lowered to a minimum angle of ____ degrees.

60