What are the processes in Cost Management knowledge area?
In which process groups are they? |
Planning - Plan Cost Mangement
Planning - Estimate costs Planning - Determine budget M & C - Control costs |
|
Life - Cycle costing
|
analyzing the total cost of ownership from creation, to operations, and finally disposal. Is meant to find unintended consequences of project.
|
|
Inputs to Plan Cost Management process?
|
Project Management plan
Project charter Common - Ent. Env, Factors, Prg. Process assets |
|
Outputs to Plan Cost Management process?
|
Cost management plan
|
|
Inputs to estimate cost process?
|
Cost Managment plan
Human REsource plan Scope Baseline Project schedule Risk register |
|
Outputs to estimate cost process?
|
Activity Cost estimates
Basis of Estimates Project document updates |
|
Inputs to determine budget process?
|
Cost Management plan
Scope baselinBasis of estimates Activity cost estimates Basis of estimates Project schedule Resource calendars risk register agreements |
|
Outputs to determine budget process?
|
Cost baseline
Project funding requirements Project document udates |
|
A budget is also known as?
|
Cost performance baseline
|
|
Inputs of Control costs process?
|
Project Management plan
Project funding requirements |
|
Outputs of Control costs process?
|
Work performance information
cost forecasts change requests Prlject Mangement plan updates Project documentation updates Organizational Process Assets Updates |