Planned Value (PV)
|
As of today, what is the estimated value of the work planned to be done?
FV / (1+r)^n |
|
Earned Value (EV)
|
As of today, what is the estimated value of the work accomplished?
|
|
Actual Cost (AC)
|
As of today, what is the cost incurred for the work accomplished?
|
|
Budget at Completion (BAC)
|
The Budget. What did we budget for the whole project?
|
|
Estimate at Completion (EAC)
|
As of today, what do we expect the total cost of the project to be?
AC + ETC |
|
Estimate to Complete (ETC)
|
As of today, what is going to cost to finish the project?
EAC - AC |
|
Variance at Completion (VAC)
|
As of today, how much over or under will we be on the budget when project completes?
BAC - EAC |
|
Cost Variance (CV)
|
EV - AC
|
|
Schedule Variance (SV)
|
EV - PV
|
|
Cost Performance Index (CPI)
|
EV / AC
|
|
Schedule Performance Index (SPI)
|
EV / PV
|