• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/11

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

11 Cards in this Set

  • Front
  • Back
Planned Value (PV)
As of today, what is the estimated value of the work planned to be done?

FV / (1+r)^n
Earned Value (EV)
As of today, what is the estimated value of the work accomplished?
Actual Cost (AC)
As of today, what is the cost incurred for the work accomplished?
Budget at Completion (BAC)
The Budget. What did we budget for the whole project?
Estimate at Completion (EAC)
As of today, what do we expect the total cost of the project to be?

AC + ETC
Estimate to Complete (ETC)
As of today, what is going to cost to finish the project?

EAC - AC
Variance at Completion (VAC)
As of today, how much over or under will we be on the budget when project completes?

BAC - EAC
Cost Variance (CV)
EV - AC
Schedule Variance (SV)
EV - PV
Cost Performance Index (CPI)
EV / AC
Schedule Performance Index (SPI)
EV / PV