Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
65 Cards in this Set
- Front
- Back
Owner's Role
|
Take leadership role in beginning of the project by setting the tone at a preconstruction meeting, or conference.
|
|
Lien
|
Recall: A legal claim against the property of another as security for the payment of debt. May give the holder a right to sell the property to satisfy the debt if it is not otherwise paid. Removed when the contract is paid.
|
|
lien waiver
|
Receipt for getting paid, nearly impossible to defend in court.
-Conditional 1. Conditional Waiver on final payment 2. Conditional waiver on progress payments. - Unconditional 3. Unconditional waiver on progress payments 4. Unconditional waiver on final payment |
|
Mechanic's lien
|
A claim created by state statute for the purpose of securing priority of payment for work on materials furnished in constructing a building or other structure, and as such the lien generally attaches to the land as well as the improvements of it.
|
|
Preconstruction Meeting
|
- Clarify lines of communication and authority.
- Attendees likely to be the owner, architect, engineers, general contractor, subcontractors, vendors, utility personnel, fire marshal, inspectors, and any other important parties to the project. - Agenda will cover all items in the general conditions and supplemental conditions portion of the contract. |
|
Schedule of Values
|
- Detailed statement furnished by construction contractor, builder or others outlining the portions of the contract sum.
- It allocates values for the various parts of the work and is also used as the basis for submitting and reviewing progress payments. |
|
RFI
|
- Requests for information
- Written request for clarification regarding some detail in the plans, specifications or both. - Every single inquiry must be documented. - General contractors often have a form that their subs must use for consistency. |
|
RFI Flow
|
Architect or Engineer
^ | General Contractor ^ | Subcontractor request |
|
Submittal
|
- Data involving samples, colors, texture, product literature, shop drawings, etc.
- Presented to the architect by contractor for approval before orders are places. - Architect checks for conformance with plans and specs. Most, if not all items to be installed will require a submittal. |
|
Final Payment
|
Can only be released when the job is totally complete - all paperwork complete, punch list approved.
|
|
Job Wrap up Requirements
|
- Certificate of Occupancy recieved
- As-built drawings delivered. - Warranties provided. - Test reports furnished. - Full lien waivers presented. |
|
Types of delay claims
|
- Non-excusable
- Excusable but non-compensable - Excusable and compensable |
|
Mediation
|
- An impartial 3rd party facilitates a negotiated settlement between the parties.
- no attorneys involved. - less time and money required |
|
Minitrial
|
- One step above mediation in complexity, time commitment and money
- Executives from both sides are involved - Attorneys are involved for both sides in a simple, brief trial with a 3rd party acting as a tie-breaker. |
|
Arbitration
|
- Binding arbitration is often the dispute resolution method stipulated in the general conditions section of the construction market.
- time consuming and costly. - Arbitrator is played by impartial 3rd party. - Arbitrator's decision is final. |
|
Litigation
|
- Dispute settlement in a court of law
- decisions made by judge or jury - Attorneys required on both sides. - Extremely time and money costly - The final option open to parties involved in a dispute. |
|
Superintendent
|
The owner's or GC's representative on site. Responsible for coordination of workers and vendors, continuous field supervision and completion of the work.
|
|
City Hall Building Department
|
permits and inspections
|
|
Zoning department
|
laws governing regulation and use
|
|
Environmental concerns associated with construction
|
- Soil erosion
- Endangered species protection - Protected vegetation - wetlands protection - Historical or cultural arifacts |
|
What percentage of north american waste is generated by construction
|
25-45%, but almost all is recyclable, and money can be saved by recycling.
|
|
Log or project diaries
|
Should be kept by every project team member, especially the super.
- Telephone calls made or recieved - Faxes sent and recieved - Submittals - Deliveries - Change orders - Requests for information |
|
Critical path
|
- Longest path, in days, through a construction schedule.
- The end is the soonest date on which a given project may be completed. - If an activity is on the crit path is delayed, the project completion date will be delayed. |
|
Keeping score
|
The basis for project debriefing, helps to improve future projects with regard to time, money, quality and safety.
|
|
Debriefing Questions
|
- What went well?
- What didn't go well? - Why did things happen? - What will we do differently and better next time? - How can we use this? |
|
Types of Activities to be Scheduled
|
1. Administrative
2. Procurement 3. Production |
|
Administrative Activities
|
- Permits
- submittals - testing - inspections - these activities can consume lots of time in your schedule, you usually have no control over this. |
|
Procurement activities
|
Obtaining materials, equipment, subcontractors
|
|
Production Activities
|
Everything associated with actual construction of a project.
- some activities do not require effort, but require time, such as concrete curing. |
|
Change Order
|
New or different labor and/or materials not reflected in the estimate.
- Installing an extra door - Installing a different door than shown on the plans and in the specifications. |
|
Crashing the schedule
|
Throw additional resources to the critical path without getting the highest level of resources.
- adding someone who will not get the job done very quickly, but will keep you on schedule to avoid late penalties. |
|
Biggest factors in a Company's profitability
|
Quality and Safety
|
|
Quality
|
- Meeting or exceeding the requirements of a project as enumerated in the plans and specs.
- Level decided by the design team and owner, as well as the cost of finer materials. |
|
Ways to manage quality
|
- Obtain good plans and specs
- Provide regular inspections - Provide adequate supervision - Accept only qualified workers - Never accept inferior work - Maintain a positive attitude toward quality. |
|
Total Quality Management
|
No matter how good your product, process or performance is, it can always be improved upon.
|
|
How to implement TQM
|
- Identify the problem
- Break it down into steps - Identify the weak link - Determine the remedy - Apply the remedy - Measure the results (is it better, worse, or the same) |
|
Quality Assurance Function
|
Deals with policies and procedures
- Hiring practices - Training - Safety - Subcontractors - prequalify |
|
Quality control function
|
Deals with quality management at the project level and addresses conformance with the plans and specs.
- tools used are + submittals + shop drawings + inspections + mockups + testing |
|
Correction Notice
|
A notice of inspection fail that allows the job to continue going.
|
|
Stop work notice
|
Notice of inspection failure where job must stop immediately.
|
|
Mock-ups
|
- Small model made of the specified components
- Need specified by contract documents - Architect may require them if any question exists as to whether the owner will be satisfied. |
|
ASTM
|
American Society for Testing Materials
- Develops voluntary standards for materials, products, systems and services. |
|
Underwriter's Laboratory
|
Independent product safety testing and certification organization, adds credit to materials and systems.
|
|
OSHA
|
Occupational Safety and Health Administration
- Gov't organization, can levy fines |
|
Prebid Risks
|
- Alone or Joint venture?
- Intended profit margin? - Contingencies |
|
Design Risks
|
Have to choose a design team and build
- Puts CM at risk |
|
Construction Risks
|
Controllable
- Safety - Productivity Uncontrollable - Mother nature - Labor availability - Labor disputes/strikes |
|
Prevailing Wage
|
- Sets minimum hourly wage and fringe benefits for workers on all federal and federally funded projects over $2,000
- Usually determined by the most recently negotiated union wage and fringe benefit rates. |
|
this sensory corpuscle is a large, encapsulated nn ending found in deeper layers of skin at ligaments, joint capsules, serous membranes, and mesenteries. It is involved in pressure, coarse touch, vibration, and tension.
|
pacinian corpuscle
|
|
Scab
|
A worker who refuses to join a union; a union member who refuses to strike or returns to work before the strike has ended.
|
|
License is Required for
|
- Architects
- Engineers - Surveyors - Residential buildings - Specialty contractors - NOT for GC |
|
GC bidding on specialty work
|
Can bid, but must hire someone else to do the work
|
|
Michigan Construction Lien Act
|
- Protects rights of contractors, vendor and employees to payment.
- Protects owners from having to pay twice for such goods and services |
|
Lien Act Requirements
|
- Notice of Commencement
- Notice of Furnishing - Sworn Statement - Waiver of lien - Claim of lien |
|
Notice of commencement
|
Advises potential lien claimants of the project owner's name, legal description of where the project is located.
- must be posted clearly on property |
|
Notice of Furnishing
|
Alerts the owner who is furnishing goods or services to a project so they can determine who has lien rights if payments aren't recieved.
|
|
Sworn Statement
|
Lists subcontractors, suppliers, laborers that the contractor or subcontractor is contracting with to complete the project.
|
|
Negotiable contract items
|
- Extended payment terms or discounted quick pay
- Late payment terms (be wary of % of sale!) - Buy out terms - Taxes and other fees - freight, fuel charges, hazmat fees, etc. - Price increases. |
|
Liquidated damages
|
Type of punitive damages where the penalty amount for a proven violation of a law or contract provision is designated in advance.
|
|
Promissory Note
|
A note is a document which serves as evidence that debt exists between a borrower and a lender, and usually contains the terms under which the loan must be repaid and the rights and responsibilities of both parties.
|
|
Items Contained in a note
|
- Interest rate
- Amount borrowed - Maturity Date - Payment + Amount, number and due dates - Collateral |
|
Plat Plan
|
Aerial view of a subdivision, shows some or all lots, includes roads, ponds, green space, natural features.
|
|
Floor Plan
|
less architecturally detailed than an architectural drawing, shows setup of room and design features rather than absolute dimensions.
|
|
Structural Plans
|
Made by structural engineers to be sure the building can withstand vertical and horizontal loads.
|
|
QuickBooks Premier Contractor Edition 2011
|
Software to help contractors plan, budget and reduce waste on jobs
|