CPI=
|
CPI = EV/AC
|
|
CV=
|
CV = EV - AC
|
|
SV=
|
SV = EV - PV
|
|
SPI=
|
SPI = EV/PV
|
|
VAC=
|
VAC = BAC - EAC
|
|
EAC =
|
EAC = BAC/CPI
|
|
SV% =
|
SV% = SV/PV x 100
|
|
CV% =
|
CV% = CV/EV x 100
|
|
% Complete =
|
EV = PV X %complete
OR (SPI x 100) = % complete |
|
ETC =
|
ETC = EAC - AC
|
|
Name the 9 Knowledge Areas
|
Integration
Scope Time Cost Quality Human Resources Communication Risk Procurement |
|
Name the 5 Process Groups (Project Domains)
|
Initiating
Planning Executing Controlling Closing |
|
Name 1 Output for "Sequence Activities"
|
Network Diagram
|
|
Name 1 Output for "Define Scope"
|
Scope Statement
|
|
Name the 2 most common inputs in planning.
|
Enterprise environmental factors
Organizational process assets |
|
The most common type of precedence relationship is _________
The most common type of network diagramming technique is called ________, also called _____________. |
Finish to start
PDM (Precedence Diagramming Method) AON (Activity on Node) |
|
Quality Audits are performed during what PM process?
|
Quality Assurance
|
|
The Critical Path Method, schedule compression, what if analysis, resource leveling, and critical chain method are tools used in what PM process?
|
Develop schedule
|
|
Validated deliverables are an output of what PM process?
|
Quality Control
|
|
How many closing processes are there, and what are they?
|
2
Close proocurement, close the project. |