• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/16

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

16 Cards in this Set

  • Front
  • Back
Project Time Management
1 Define Activities
 Identify activities
 constraints
 assumptions
2 Sequence Activities
 task order
 inter-dependencies
 phases and gates
3 Estimate Activity Resources
 resource required
4 Estimate Activity Duration
 time needed to implement
5 Develop Schedule
 analysis of patterns
 fine tuning
6 Control Schedule
 controlling changes
Define Activities - I-TT-O

The process of identifying the specific actions to be performed to
produce the project deliverables
Inputs
• Scope baseline
• Enterprise environmental
factors
•Organizational process
assets

Tools and
Techniques
• Decomposition
• Templates
• Rolling wave
planning
• Expert judgment

Outputs
• Activity list
• Activity
Attributes
•Milestone list
Sequence Activities I-TT-O

The process of identifying and documenting relationships among
the project activities
Inputs
• Activity list
• Activity attributes
•Milestone list
• Project scope
statement
•Organizational
process assets

Tools and
Techniques
• Precedence
diagramming method
(PDM)
• Dependency
determination
• Applying leads and lags
• Schedule network
template

Outputs
• Project schedule
network diagram
• Project document
updates
Precedence diagramming method (PDM)
 Basis for Gantt charts
 Most commonly used approach
Estimate Activity Resources I-TT-O
The process of estimating the type and quantities of material ,
people, equipment or supplies
Inputs
• Activity list
• Activity attributes
• Resource calendars
• Enterprise
environmental factors
•Organizational process
assets

Tools and
Techniques
• Expert judgment
• Alternative
analysis
• Published
estimating data
• Bottom up
estimating
• Project
management
software

Outputs
• Activity resource
requirements
• Resource breakdown
Structure
• Project document
updates
Estimate Activity Resources
Estimate resources required
 What resources are available to be allocated to each task?
 Sources for estimates:
 Personal Experience / Knowledge / Records
 Information from other peoples experience etc.
 Published information
 Resource Allocation
 Initial assumption is that we allocate “normal” resources to
every activity
 i.e. the basic resources needed to carry out an activity in the
manner which usual practice dictates and without working
abnormal hours
Estimate Activity Durations -I-TT-O
Assessing the number of work periods likely to be
needed to complete each identified activity
Inputs
• Activity list
• Activity attributes
• Activity resource
requirements
• Resource calendars
• Project scope statement
• Enterprise environmental
factors
•Organizational process
assets

Tools and
Techniques
• Expert judgment
• Analogous estimating
• Parametric estimating
• Three-point estimates
• Reserve analysis

Outputs
• Activity duration
estimates
• Project document
updates
PERT Method
t = (o+4m+p)/6
Where
t = the estimated time
o = optimistic time
m = most likely time
p = pessimistic time
Develop Schedule I-TT-O

Process of analyzing activity sequences, duration, resource
requirements and schedule constraints to create project schedule
Inputs
• Activity list
• Activity attributes
• Project schedule network
diagrams
• Activity resource
requirements
• Resource calendars
• Activity duration
estimates
• Project scope statement
• Enterprise environmental
factors
•Organizational process

Tools and
Techniques
• Schedule network
analysis
• Critical path method
• Critical chain method
• Resource leveling
•What-if scenario
analysis
• Applying leads and lags
• Schedule compression
• Scheduling tool

Outputs
• Project schedule
• Schedule baseline
• Schedule data
• Project document
updates
The Critical Path:
The series of activities that...
 Determine the earliest possible completion
date for the project
 Forms the longest total anticipated duration
period
 Can change the project completion date, if
any are delayed
 Have total float equal to zero
Scheduling with RESOURCE
Constraints
If we only have a limited resource pool and our
original assumptions were based on unlimited
resources, then we have the following possibilities:
 Review original duration calculations
 Review original Network Logic
 Look at possible Activity overlaps
 Use “Float” times to “balance” resources
 Work additional hours with available resources
 Extend Project Duration
Control Schedule I-TT-O
Process of monitoring the status of the project to update project
progress and manage changes to the schedule baseline
Inputs
• Project
management plan
• Project schedule
•Work performance
information
•Organizational
process assets

Tools and
Techniques
• Performance reviews
• Variance analysis
• Project management
software
• Resource leveling
•What-if scenario
analysis
• Schedule comparison
• Scheduling tool

Outputs
•Work performance
measurements
•Organization process
assets updates
• Change requests
• Project management
plan updates
• Project document
updates
Types of Costs
 Direct costs
 Costs incurred directly by
the project
 Readily identified
 Indirect costs
 Costs allocated to the
project by the
organization
 Cost of doing business
 Fixed costs
 Will be constant,
regardless of the size of
the project
 Variable costs
 Will vary in size with the
size of the project
 Related to specific
project parameters or
objectives
Types of Costs
 Sunk cost
 Cannot be recovered
 Costs already expended
 Opportunity costs
 Benefits not realized due
to choosing a particular
alternative
 Not a true cost, and
difficult to confirm
 Expense
 Cost deducted against
income for current year
 Related to operations
 Capital Costs
 Not an expense,
depreciated over time
 Related to projects
Estimate Costs I-TT-O
Developing an approximation of the monetary
resources needed to complete project activities
Inputs
• Scope baseline
• Project schedule
• Human resource plan
• Risk register
• Enterprise
environmental factors
•Organizational process
assets

Tools and
Techniques
• Expert judgment
• Analogous estimating
• Parametric estimating
• Bottom-up estimating
• Three point estimates
• Reserve Analysis
• Cost of quality
• Project management
estimating software
• Vendor bid analysis

Outputs
• Activity cost
estimates
• Basis of estimates
• Project document
updates
Estimate Classes
Definitive -5% to 10%
Budget -10% to +15%
Order of Magnitude -50% to 100%