• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/17

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

17 Cards in this Set

  • Front
  • Back
Project Cost Management
Includes the processes involved in
estimating, budgeting and controlling costs so
that the project can be completed within the
approved budget.

Estimate Costs
 Determine Budget
 Control Costs
Estimate Classes
Analogous (Top-Down) Estimating
 Used for Class 6 - Order of Magnitude
 Compare total costs for similar projects
 Advantages
 Fast, understandable, inexpensive
 Information may be readily available
 Based on actual cost expenditures
 Disadvantages
 Lack of similar projects
 Lack of reliable information
Detailed (Bottom-Up) Estimating
 Used for Class 1 - Definitive Estimates
 Requires detailed measurement of all
components (e.g. quantity surveying)
 Uses established rates for each part, based
on industry standards, known labour input,
and supplier costs
 Possible only when the design and
specifications are complete
Parametric Modelling
 Use formulae derived from projects
 Two methods are available to calculate a parametric formula
1 Statistical analysis
2 Logical analysis
 Either approach can result in a valid models
 Both require recent data from similar projects
 For Detailed Estimates - Class 2 or 3
 Use complex models from extensive statistical or logical
analysis
 Best to use separate value for each parameter
 For Preliminary Estimates - Class 4 or 5
 Use simple models based on average rates
Detailed Cost Estimating Process
 Use formulae derived from projects
 Two methods are available to calculate a parametric formula
1 Statistical analysis
2 Logical analysis
 Either approach can result in a valid models
 Both require recent data from similar projects
 For Detailed Estimates - Class 2 or 3
 Use complex models from extensive statistical or logical
analysis
 Best to use separate value for each parameter
 For Preliminary Estimates - Class 4 or 5
 Use simple models based on average rates
Determine Budget I-TT-O

Process of aggregating the estimated costs
of individual activities or work packages to
establish an authorized cost base line
Inputs
• Activity cost estimates
• Bases of estimates
• Scope baseline
• Project schedule
• Resource calendar
• Contracts
•Organizational process
assets

Tools and
Techniques
• Cost aggregation
• Reserve analysis
• Expert judgment
• Historical relationships
• Funding limit
reconciliation

Outputs
• Cost performance
baseline
• Project funding
requirements
• Project document
updates
Control Costs I-TT-O

 Monitoring cost performance to detect variances
from the baseline
 Ensuring that all appropriate changes are recorded
accurately and authorized
Inputs
• Project management
plan
• Project funding
requirements
•Work performance
information
•Organizational
process assets

Tools and
Techniques
• Earned value
management
• Forecasting
• To complete
performance index
• Performance reviews
• Variance analysis
• Project management
software

Outputs
•Work performance
measurements
• Budget forecasts
•Organizational process
assets updates
• Change requests
• Project management
plan updates
• Project document
updates
Earned Value Management:
The Key Components
1 PLANNED VALUE (PV): What did we plan to achieve by now?
 also called: the budgeted cost of the work scheduled (BCWS)
 the portion of the approved cost estimate planned to be spent on
the activity during a given period
 includes both direct and indirect costs
2 EARNED VALUE (EV): What have we achieved so far?
 also called: the budgeted cost of the work performed (BCWP)
 a percentage of the total budget equal to the percentage of the
work actually completed
 can include an estimated value for partly completed activities
3 ACTUAL COST (AC) What have we spent so far?
 also called: the actual cost of the work performed (ACWP)
 the total of direct and indirect costs incurred in accomplishing
work on the activity in a given period
Determining the Earned Value of a
Work Package
 Not started: No earned value (of course)
 Completed: Earned value is equal to the planned
value for that task
 In progress: Different ways to calculate:
 Percent complete – Based on reports from staff
 Effort Left - Input from staff
 The 0/100 Rule – No value given until task is complete
 The 50/50 Rule – Task is given half the PV when started,
the balance when completed
 Other approaches can be used for certain tasks
Cost Variance
CV = earned value - actual cost = BCWP - ACWP
CV = EV - AC
negative CV is the $ value that performance lags behind costs
Schedule Variance
SV = earned value - planned value = BCWP - BCWS
SV = EV - PV
negative SV is the $ value that performance is behind plan
Cost Performance Index
CPI = earned value / actual cost = BCWP / ACWP
CPI = EV/AC
CPI gives performance as a ratio of actual costs to date
Schedule Performance Index
SPI = earned value / planned value = BCWP / BCWS
SPI = EV/PV
SPI gives performance as a ratio of the budget to date
Estimated Actual Cost ( end of project)
EAC = Total Budget / CPI
To-complete Performance Index
(TCPI)
Calculated projection of cost performance
that must be achieved on the remaining work
to meet specified management goal

TCPI = Work Remaining(BAC-EV) /
Funds Remaining (BAC-AC) or (EAC-AC)
Earned Value Management
SV - Schedule Variance
SV = EV - PV
SPI - Schedule Performance Index
SPI = EV / PV
CV - Cost Variance
CV = EV - AC
CPI - Cost Performance Index
CPI = EV / AC