Use LEFT and RIGHT arrow keys to navigate between flashcards;
Use UP and DOWN arrow keys to flip the card;
H to show hint;
A reads text to speech;
27 Cards in this Set
- Front
- Back
An interrelated set of activities with a definite starting and ending point, which results in a unique outcome for a specific allocation of resources.
|
Project
|
|
A systemized, phased approach to defining, organizing, planning, monitoring, and controlling projects.
|
Project Managment
|
|
An interdependent set of projects that have a common strategic purpose.
|
Program
|
|
A statemetn of all work has to be completed.
|
Work breakdown structure
|
|
The smallest unit of work effort consuming both time and resources that the project manager can schdule and control.
|
Acitivity
|
|
A network planning method, designed to depict the relationships between activities, that consists of nodes and arcs.
|
Network diagram
|
|
A networking planning method created for the US Navy's Polaris missile project in the 1950s which involved 3,000 separate contractors and suppliers
|
Program evaluation and review technique (PERT)
|
|
A network planning method developed in the 1950s as a means of scheduling maintenance shutdowns at chemical processing plants.
|
Critial Path Method (CPM)
|
|
A relationship that determines a sequence for undertaking activiites; it specifies that one activity cannot start until a preceding activity has been completed.
|
Precedence Relationship
|
|
An approach used to create a metwork diagram, in which nodes represent activities and arcs represent the precedence relationships between them.
|
Activity - on - note (AON) network
|
|
The sequence of activites between a project's start and finish.
|
Path
|
|
The sequence of activities between a project's start and finish that takes the longest time to complete.
|
Critical Path
|
|
An activity's earliest start time plus its estimated duration EF = ES + t.
|
Earliest Finish Time (EF)
|
|
The latest start time of the activity that immediately follows.
|
Latest Finish TIme (LF)
|
|
The latest finish time minus its estimated duration. LS = LF - t
|
Latest Start Time (LS)
|
|
The maximum length of time that an activity can be delayed without delaying the entire project
|
Activity Slack
|
|
A project schedule usually created by the project manager using computer software, that superimposes project activities, with their precendence relationships and estimated duration times, on a time line.
|
Gantt Chart
|
|
The time necessary to complete an activity under normal condiitons
|
Normal Time
|
|
The activity cost associated with normal time.
|
Normal costs
|
|
The shortest possible time to complete an activity
|
Crash Time
|
|
The activity cost associated with the crash time
|
Crash Cost
|
|
A schedule determined by starting with the normal time schedule and crashing activities along the critical path in such a way that the costs of crashing do not exceed the savings in indirect and penalty costs.
|
Minimum-Cost Schedule
|
|
A plan that identifies the key risks to a project's success and prescribes ways to circumvent them.
|
Risk-Management Plan
|
|
The shortest time in which an activity can be completed if all goes exceptionally well.
|
Optimistic Time
|
|
The probable time required to perform an activity.
|
Most Likely Time
|
|
The longest estimated time required to perform an activity.
|
Pessimistic Time
|
|
An activity that includes writing final reports, completing remaining deliverables, and compliling the team's recommendations for improving the project process.
|
Close Out
|