• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/14

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

14 Cards in this Set

  • Front
  • Back

Why Bid?

Profits


Need to establish or maintain relationship with a new client


Unusual project to add variety to the portfolio


High publicity probability or benefits to the community

Factors That Makes One Company Succeed Over Another

Relationship with key subcontractors


Expertise in the type of project


Estimating capability


Project team set-up


Safety record


Ability to work efficiently


Overhead costs

Elements of a Bid

Estimate


Solicit prices from a number of subs


Subs perform material takeoffs from the drawings and specifications that result in the quantities required on the job.


These quantities are then multiplied by the unit cost.


The unit cost is established by talking with vendors and suppliers


Direct cost + Indirect costs = Cost of the work


Cost of the work + % of overhead and profit = Total cost to the owner

Bidder Qualification Process

Two methods


Pre-bid


Requires the interested contractor to submit information about the firm before the bid documents are released.


This is done while contract documents are being finalized to save time.


Advantages of prequalifying bidders


When the bids are received, the lowest bidder can be selected.


Saves time and potential disputes from disqualified bidders after the bid based on financial or technical abilities

Pre-Bid Qualification

Even with the prequalifying process, bidders can be disqualified. How?


Not following the terms of the contract documents


Offering material or methods that are different from what was expectedTypically between five and seven bidders for each major trade, but no less than three

Work Packages

One of the advantages of Construction Management delivery method is the ability to package the work to the best advantage of the project in terms of price and efficiency


It also allows fast tracking of the work so the parts of the project can be bid and started before the entire design package is assembled


Even if the project is completely designed before it is bid, there are number of advantages to breaking the project into various work packages.

Advantages of Work Packages

Allows for the incorporation of local practices


Packaging work reduces overhead:


The more packages, the fewer markups.


Requires that a large number of subcontractors must be managed directly.


Too little layering of subs affects both price, time, and quality of the project


Subs may be contracted directly to either the owner or CM . In either case, the owner is involved in the selection process

Disadvantage of Work Packages

Omission of responsibilities resulting in change orders or a dispute


Drilling cores to run conduits


Patching after the conduit is run


Furnishing scaffolding to multiple trades


Clean upRedundancy of work - Two or more trades may end up with part of the same scope


Mechanical contractor has control wiring as well as the electrical contractor


Disadvantages of Work Packages


Poor Coordination


Improper packaging of work – If the work is not bid properly, there might be little interest or the bids will come in high. The CM must package the work correctly


Breaking work packages into individual bid packages is best done by CMs

Construction Documents

Translates owner needs for the contractor


Communication link among all parties in the project


All narrative information is packaged with drawings in one binder (or several binders) to make up a complete package


Construction Documents (Continued)Package is divided into three general sections


Bidding


Contractual


Technical

Bidding Information

Invitation to bid - Is the request for pricing. The owner usually prepares it with the help of the CM or designer. It includes information that is relevant to the project


The type of project


The size of the project


The location of the project


Bid due date


Start and completion dates


Bonds


Document location


Legal requirements


Instruction to the bidders


Bid due date


Instructions about filling out the form


Places to indicate fees for additional work


Unit Prices


Location to deliver the bid


Method of awarding the bids


Expected dates of awards and start of the project


Bid form


Name of the contractor


Price


Price breakdown for the major trades


Amount of the bond


Alternates (materials or altered scope of work


Fees for additional work


Unit pricing if quantities are unclear


Time required for the job


Acknowledgement of receipt of all addenda issued after the bids have gone out


Key Subs


Signature, title, and date


Alternates – An alternate is a request for a price for substituting one material for another, for adding to the scope of work, or for deducting from the scope


Two ways to present alternates


Additive price. This is the best method for the owner since it is priced as a new item. This brings in a better price.


Deductive price. Might leave some of the cost in the price. Designers prefer this because they can produce a complete set of documents that can then be deducted from more easily.


Addenda – After the documents are issued but before the bids are due, changes often need to be made.


The most common reason is to correct mistakes in the bidding documents.


Contractors really study the drawings and often find things that are missed by designers or drafters


Contractor may propose a better method


Owner may generate additional requests.


Sometime addenda simply completes documents that had to be sent out before being totally complete

Contractual Information

Agreement


General Conditions


Special Conditions


Bonds


Insurance


Agreement


Identification of the parties


Description of the project and the work


Start date


Substantial completion date


Liquidated damages


Agreement (continued)The contract sum


Progress payments


Interest rates


Retainage


Final Payments


Enumeration of contract drawings


General Conditions


Special Conditions


Bonds


Bid Bonds


Performance Bonds


Payment Bond


Insurance


Worker’s Compensation


Comprehensive Liability


Builder’s Risk

Technical Information

Drawings.


Specifications


Design specifications


Performance specifications


Proprietary specifications


Open Specifications

Analysis of Bids

The bids are tabulated in a spreadsheet. The owner and CM must evaluate the assumptions and make sure that they are reasonable.


If bidders provide pricing that is outside the plans and specifications, the project needs to decide how to handle this.


If the bidder who is low, even without an alternative, suggests an equal to or better alternate that makes him even lower, the owner has the option of accepting


If the bidder who is not low provides an unequal but acceptable alternate that then makes him low, the owner has the option of giving the other bidders the opportunity to bid this alternate as wellIf the bidder who is not low and won’t ever be low suggests an acceptable alternative, the owner has the option of having the low bidder price this alternate

Award of the Contract

The owner has the right to reject or accept the bids


In most cases, a project does not get bid if the estimates are higher than the money available to complete the project


If the bids are higher, the normal procedure is to redesign or reduce scope


Redesigning is time consuming, however, so the owner may elect to work with the bidder to bring down the price through value engineering, cost cutting, or scope reduction


Once the bid is accepted, the contract negotiations begin. This is a straight forward process since the contractor has already seen the contract.


While negotiations are ongoing, the owner may send a letter of intent which states a specific time period, methods of payments, and conditions of termination if the negotiations fall through.