• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/13

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

13 Cards in this Set

  • Front
  • Back

it is a heavy construction equipment consisting of a boom, stick, bucket and a cab on a rotating platform

EXCAVATOR

Used extensively in construction work to handle and transport bulk material, such as earth and rock; to load trucks; to excavate earth; and to charge aggregate bins at asphalt and concrete plants.

LOADER

Requires a thorough knowledge of the construction procedures and cost of materials & labour in addition to the skill, experience, foresight and good judgment.

Cost estimation

Prepared by carefully and separately calculating in detail the costs of various items of the work that constitute the whole project from the detailed working drawings after the design has been finalized

OVERHEAD COST

Provide greater mobility between job sites, but require better surfaces for their operation.

WHEEL MOUNTING

They are typically mounted on the back of a tractor or front loader.

BACKHOE

This is Suitable for moving soil for short distances only, up to about ______

50 METERS

The quantities for each item may be estimated and shown in the pattern which is called _____

BILL OF QUANTITIES

The blade mounted on this tractor can be rotated about a vertical axis as well as raised and lowered to permit side casting of materials.

ANGLE DOZER

Scraper are best suited to haul distances greater than 500 ft. but less than ______

3,000 FT

Used for excavation and removal of overburden in open cut mining operation, though it may include loading of minerals such as coal.

POWER SHOVEL

Are employed in the early planning phases of a proposed project to match client needs, assessed requirements and budget constraints in order to establish project scope and quality expectations.


SCREENING ESTIMATES

Must be adopted early enough for planning long term financing of the facility.

BUDGET ESTIMATE