1/75

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

75 Cards in this Set

  • Front
  • Back
  • 3rd side (hint)

Assumption Log

Record of all assumptions & constraints that affect the project.

Record

What is an assumption?

A factor in the planning process that is true, real, or certain without proof or demonstration.

What do you use the assumption log for?

May help identify items that have not been closed or managed.

Basis of Estimates

Shows how the duration, cost, & resources estimates were calculated to determine any variances from what was planned.

Change Log

A comprehensive list of changes submitted during the project.

Issue Log

A log that documents all issues & is critical for this process to ensure that all issues have been addressed in the Close Project or Phase process.

Lessons Learned Register

A record of knowledge gained throughout the project that shows how project tasks were addressed or should be addressed in the future to improve performance.

Milestone List

Identifies all significant points or events in the project & indicates whether the milestone was mandatory or not.

Project Communications

Reference for all communications that have been created throughout the project.

Quality Control Measurements

Documents the results of Control Quality activities so you can ensure the project's objectives satisfy stakeholders' expectations.

Quality Reports

Provides a summary of findings from the Control Quality process, including quality management issues as well as recommendations for improvements.

Requirements Documentation

Used to demonstrate compliance with the project scope.

Risk Register

A repository with details of all identified individual project risks. Valuable reference on risks that have occured throughout the project.

Risk Report

Provides information on sources of overall project risk & summary information on individual project risks. Valuable to check that there are no open risks at the end of the project.

Project Documents

Assumption Log, Basis of Estimates, Change Log, Issue Log, Lessons Learned Register, Milestone List, Project Communications, Quality Control Measurements, Quality Reports, Requirements Documentation, Risk Register, Risk Report

Organizational Process Assets (OPAs)

Plans, processes, policies, procedures, & knowledge bases that are specific to and used by a performing organization.

Stakeholder Register

Used to identify those people & organizations impacted by the project. This document includes the identification, assessment, & classification or project stakeholders.

Project Charter

Document issued by the project initiator or sponsor that formally authorizes the existence of a project & provides the project manager with the authority to apply organizational resources to project activities.

Project Management Plan

A document that describes how the project will be executed, monitored & controlled, and closed.

Close Project or Phase Inputs

Organizational Process Assets, Agreements, Project Documents, Project Charter, Project Management Plan, Accepted Deliverables, Business Documents, Procurement Documentation

Close Project or Phase Outputs

Project Documents Updates, Final Product, Service, or Result Transition, Organizational Process Assets Updates, Final Report

Close Project or Phase Tools & Techniques

Expert Judgement, Meetings, Data Analysis

What is part of the Project Performance Summary in the final report?

Scope Objectives, Quality Objectives, Cost Objectives & Schedule Objectives

What type of projects use an approved version of the project scope statement, WBS & associated WBS dictionary as the scope baseline for the project?

Predictive Projects

Project Scope

The work performed to deliver a product, service or result with specified features & functions

Product Scope

The features and functions of a product, service or result

What does the Validate Scope process do?

Gives formal acceptance of completed project deliverables.

What are the outputs of Plan Scope Management?

Scope management plan & requirements management plan

What are tools & techniques of Plan Scope Management?

Expert judgement, data analysis (alternatives analysis) & meetings

What is the scope management plan?

Documents how the project & product scope will be defined, developed, monitored, validated, & controlled

What are the inputs of Plan Scope Management?

Project charter, project management plan (quality management plan, project life cycle description, development approach), EEFs, & OPAs

What links product requirements from their origin to the deliverables that satisfy them?

Traceability Matrix

What requirement describes temporary capabilities needed to move from the current as-is state to the desired future state?

Transition & readiness requirements

What is the main purpose of the stakeholder register?

Identify stakeholders who can provide information on the requirements

What are the inputs of the Collect Requirements process?

OPAs, EEFs, Project Documents, Project Management Plan, Agreements, Project Charter, Business Documents

What are the outputs of the Collect Requirements process?

Requirements Traceability Matrix & Requirements Documentation

What are the tools & techniques of the Collect Requirements process?

Data Gathering, Data Analysis, Data Representation, Context Diagram, Interpersonal & Team Skills, Expert Judgement, Decision Making, Decision Making, Protoype

What are the inputs of the Define Scope process?

Project Charter, project management plan, project document, EEFs, OPAs

What are the outputs of the Define Scope process?

Project scope statement, project documents updates (assumption log, requirements documentation, requirements traceability matrix, stakeholder register)

What is the key benefit of creating a Work Breakdown Structure?

It provides a framework for what has to be delivered

What is a Work Breakdown Structre (WBS)?

A hierarchical decomposition of the total scope of work to be carried out to accomplish project objectives & create required deliverables

What are outputs of the Create WBS process?

Scope baseline, project documents updates

What are inputs of the Validate Scope Process?

Verified Deliverables, Project Documents, Project Management Plan, Work Performance Data

Define verified deliverables

Completed project deliverables that have been checked & confirmed for correctness through the Control Quality process

What are outputs of the Validate Scope process?

Accepted deliverables, Work performance information, Project documents updates, Change requests

What are the tools & techniques of the Validate scope process?

Decision making & Inspection

What are the outputs of the Control Scope Process?

Work performance information; change requests; project management plan updates (scope management plan, scope baseline, schedule baseline, cost baseline, performance measurement baseline); project ducoments updates ( lessons learned register, requirements documentation, requirements traceability matrix)

What is Control Scope?

The process of monitoring the status of the project & product scope & managing changes to the scope baseline.

What are the tools & techniques of the Control Scope process?

Data analysis (variance analysis, trend analysis)

What are the inputs of the Control Scope Process?

Project management plan; (scope management plan, requirements management plan, change management plan, configuration management plan, scope baseline, performance measurement baseline); project documents (lessons learned register, requirements documentation, requirements traceability matrix); work performance data; OPAs

What are some considerations for tailoring for project schedule management?

Life cycle approach, resource availability, project dimensions & technology support

Develop Schedule is the process of what?

Analyzing activity sequences, durations, resource requirements, & schedule constraints to create the project schedule module for project execution & monitoring & controlling

Plan Schedule Managment is the process of what?

Establishing policies, procedures & documentation for planning, developing, managing, executing & controlling the project schedule.

What is the output of Plan Schedule Management?

Schedule management plan

Schedule Management Plan establishes what?



Criteria & activities for developing, monitoring & controlling the schedule

What are the tools & techniques of Plan Schedule Management?

Expert judgement, data analysis(alternative analysis) & meetings

What are the inputs for the Plan Schedule Management Process?

Project Charter, project management plan(scope management plan, development approach), EEFs, OPAs

Who should be included in a project schedule development meeting?

Project manager, project sponsor, selected project team members, selected stakeholders, anyone w/responsibility for schedule planning or execution

What are the tools & techniques of the Monitor Communications process?

Expert judgement, project management information system, data representation, interpersonal & team skills, team meetings

Which of the following is a tailoring consideration for Project Scope Management?

Stability of Requirements

All of the following are true about the project scope statement except:

It is an output of the validate scope process

What are inputs to the Sequence Activities Process?

Project management plan (schedule management plan, scope baseline); project documents (activity attributes, activity list, assumption log, milestone list); EEFs, OPAs

In earned value management, the cost variance is equal to:

(CV = EV - AC)

The engagement level of stakeholders can be classified as:

Unaware, resistant, neutral, supportive, and leading

What are considerations for tailoring in Project Quality Management?

policy compliance & auditing, standards & regulatory compliance, continuous improvement, & stakeholder engagement

What is SWOT analysis?

Examines the degree to which organizational strengths may offset threats & determines if weaknesses might hinder opportunities

What are 5 alternative strategies for dealing with threats?

Escalate, avoid, transfer, mitigate, accept

How many processes belong to the Planning Process Group?

24 out of 49 processes

How many processes belong to the Executing Process Group?

10 out of 49 project management processes

How many processes belong to the Monitoring & Controlling Process Group?

12 out of 49 project management processes

How many processes belong to the Closing Process group?

1 out of 49 project management processes

What is a contingency reserve?

Time or money allocated in the schedule or cost baseline for known risks w/active response strategies.

What are the Project Cost Management processes?

Plan cost management, estimate costs, determine budget, control costs

What is Earned Value Management (EVM)?

Methodology that combines scope, schedule, & resource measurements to assess project performance & progress against the project baseline.

What is Earned Schedule (ES)?

Replaces the schedule variance measures used in traditional EVM (earned value - planned value) with ES & actual time (AT)