- Front
- Back
# of days for the owner to cancel a home solicitation contract.
|
3 business days after midnight of the day it was signed.
|
|
How long do you have to retain copies of contracts and change orders ect.
|
5 years
|
|
After the home improvement contract has been canceled how many day do you have to return any down payment
|
10 from the date that they canceled the contract
|
|
How long do you have to renew an expired license
|
5 years
|
|
If you are given a citation from the Registar of contractors for a violation, how long due you have to file an appeal
|
15 days
|
|
How often must you renew an active license
|
every 2 years
|
|
How many day do you have to begin work on a home improvement contract
|
20 days
|
|
If you change your address. How many day do you have to inform CSLB
|
90 day from the date it changed
|
|
How many days after you pass the exam must you apply for your license
|
90 days
|
|
How many days do you have to replace a RMO or a RME
|
90 day from the day the rmo or rme gave notice to cslb
|
|
how many days do you have to pay wages to a fired employee.
|
0 day it must be paid immediately
|
|
how many days do you have to pay wages to a employee that quit.
|
3 days
|
|
When must you notify cal-osha of an emploee fatality
|
Immediately
|
|
when must you notify cal-osha of a serious injury.
|
Immediately
|
|
When must you notify your insurance company of an accident.
|
with in 5 days
|
|
when must you notify CSLB that you have gotten workers comp.
|
90 days
|
|
when must cal-osha investigate a serious complaint by
|
within 3 days
|
|
Liens mus go to trial within
|
2 years
|
|
When must the owner post or file a notice of non-responsability
|
10 days
|
|
Record a notice of completion
|
10 days
|
|
When must you file a forclosure / Lis Pendens action
|
90 days frome date the lien was filed
|
|
how long does the prime have to file a lien if notice of completion has been filed
|
60 days from the date notice was filed
|
|
how long does the sub have to file a lien if a notice of completion was filed
|
30 days days from the date notice was filed
|
|
How many days does the prime and sub have to file a lien if no notice of completion was filed
|
90 days from completion
|
|
you must keep all pay roll records for how long ?
|
5 years
|
|
who is FICA ?
|
Fedral Insurance Contribution Act (Social Security)
|
|
Who pays FICA?
|
50% employer and 50% employee
|
|
How often is FICA paid.
|
Quarterly
|
|
Who do you pay FICA to
|
IRS
|
|
When you become an employer. When must you register with EDD
|
within 15 days .
|
|
Who is EDD
|
EDD takes care of state unemployment and state disbility
|
|
who pays edd for unemployment
|
the employer
|
|
who pays state disability
|
the employee
|
|
Who is FUTA
|
The Fedral Unemployment Tax Act
|
|
Who pays FUTA
|
the employer up to 6.2% of the first $7000 in wages paid to the employee
|
|
When must you get a permit from OSHA
|
before an employee enters a trench deeper than 5 feet or for scafolding or demolition of three stories or more.
|