• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/3

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

3 Cards in this Set

  • Front
  • Back
Download more answer at www.ashfordhomeworks.com
Download exams at http://www.ashfordhomeworks.com/download/bus-461-week-3-quiz/
1. Question : In a maximal flow problem:Multiple sources may be accommodated, but multiple sinks may not.Arc capacities must be the same in either direction.There are several different linear programming formulations for the model.The connected arcs may contain no cycles.2. Question : A PERT/CPM network can be represented as a linear programming model by letting the decision variables be the activity start times.TrueFalse3. Question : Which of the following is true about an intermediate node in a transshipment problem?The net flow out must be zero.The node must connect to at least one supply node and at least one demand node.The number of arcs connected to supply nodes must be less than or equal to the number of arcs connected to demand nodes.The total capacity of outbound arcs must equal the total capacity of inbound arcs.4. Question : Any attempt at resource leveling always will involve lengthening the project completion time beyond its “non-leveled” minimum.TrueFalse5. Question : Minimal spanning tree problems do not lend themselves to a convenient linear programming formulation. (True, medium)TrueFalse6. Question : A B-1 bomber must fly through a choice of “safe areas,” deliver its bombing payload, and return to its home base using minimum fuel. Which network model would be the most appropriate representation?Shortest pathMinimal spanning treeTraveling salesmanTransportation7. Question : In which of the following network models is it not possible to “ship” both in and out of a given node?TransshipmentTraveling salesmanMaximal flowAssignment8. Question : An environmental impact report for a proposed new industrial center complex must include the total amount of sewage that can be pumped through existing pipes. Which network model would be the most appropriate representation?Shortest pathMinimal spanning treeTraveling salesmanMaximal flow9. Question : You can solve the traveling salesman problem by selecting a cycle with the lowest cost.TrueFalse10. Question : Using the Critical Path Method, the normal time to complete activity D is 10 weeks, and its normal cost is $500. Under maximum crashing, activity D can be completed is 4 weeks for $2,300. Therefore, if $1,100 is spent on activity D, its completion time will be 6 weeks.TrueFalse 
http://www.ashfordhomeworks.com/download/bus-461-week-3-quiz/Download answer at http://www.ashfordhomeworks.com/download/bus-461-week-3-quiz/
1. Question : In a maximal flow problem:Multiple sources may be accommodated, but multiple sinks may not.Arc capacities must be the same in either direction.There are several different linear programming formulations for the model.The connected arcs may contain no cycles.2. Question : A PERT/CPM network can be represented as a linear programming model by letting the decision variables be the activity start times.TrueFalse3. Question : Which of the following is true about an intermediate node in a transshipment problem?The net flow out must be zero.The node must connect to at least one supply node and at least one demand node.The number of arcs connected to supply nodes must be less than or equal to the number of arcs connected to demand nodes.The total capacity of outbound arcs must equal the total capacity of inbound arcs.4. Question : Any attempt at resource leveling always will involve lengthening the project completion time beyond its “non-leveled” minimum.TrueFalse5. Question : Minimal spanning tree problems do not lend themselves to a convenient linear programming formulation. (True, medium)TrueFalse6. Question : A B-1 bomber must fly through a choice of “safe areas,” deliver its bombing payload, and return to its home base using minimum fuel. Which network model would be the most appropriate representation?Shortest pathMinimal spanning treeTraveling salesmanTransportation7. Question : In which of the following network models is it not possible to “ship” both in and out of a given node?TransshipmentTraveling salesmanMaximal flowAssignment8. Question : An environmental impact report for a proposed new industrial center complex must include the total amount of sewage that can be pumped through existing pipes. Which network model would be the most appropriate representation?Shortest pathMinimal spanning treeTraveling salesmanMaximal flow9. Question : You can solve the traveling salesman problem by selecting a cycle with the lowest cost.TrueFalse10. Question : Using the Critical Path Method, the normal time to complete activity D is 10 weeks, and its normal cost is $500. Under maximum crashing, activity D can be completed is 4 weeks for $2,300. Therefore, if $1,100 is spent on activity D, its completion time will be 6 weeks.TrueFalse 
http://www.ashfordhomeworks.com/download/bus-461-week-3-quiz/
Download exams at http://www.ashfordhomeworks.com/download/bus-461-week-3-quiz/
1. Question : In a maximal flow problem:Multiple sources may be accommodated, but multiple sinks may not.Arc capacities must be the same in either direction.There are several different linear programming formulations for the model.The connected arcs may contain no cycles.2. Question : A PERT/CPM network can be represented as a linear programming model by letting the decision variables be the activity start times.TrueFalse3. Question : Which of the following is true about an intermediate node in a transshipment problem?The net flow out must be zero.The node must connect to at least one supply node and at least one demand node.The number of arcs connected to supply nodes must be less than or equal to the number of arcs connected to demand nodes.The total capacity of outbound arcs must equal the total capacity of inbound arcs.4. Question : Any attempt at resource leveling always will involve lengthening the project completion time beyond its “non-leveled” minimum.TrueFalse5. Question : Minimal spanning tree problems do not lend themselves to a convenient linear programming formulation. (True, medium)TrueFalse6. Question : A B-1 bomber must fly through a choice of “safe areas,” deliver its bombing payload, and return to its home base using minimum fuel. Which network model would be the most appropriate representation?Shortest pathMinimal spanning treeTraveling salesmanTransportation7. Question : In which of the following network models is it not possible to “ship” both in and out of a given node?TransshipmentTraveling salesmanMaximal flowAssignment8. Question : An environmental impact report for a proposed new industrial center complex must include the total amount of sewage that can be pumped through existing pipes. Which network model would be the most appropriate representation?Shortest pathMinimal spanning treeTraveling salesmanMaximal flow9. Question : You can solve the traveling salesman problem by selecting a cycle with the lowest cost.TrueFalse10. Question : Using the Critical Path Method, the normal time to complete activity D is 10 weeks, and its normal cost is $500. Under maximum crashing, activity D can be completed is 4 weeks for $2,300. Therefore, if $1,100 is spent on activity D, its completion time will be 6 weeks.TrueFalse 
http://www.ashfordhomeworks.com/download/bus-461-week-3-quiz/Download answer at http://www.ashfordhomeworks.com/download/bus-461-week-3-quiz/
1. Question : In a maximal flow problem:Multiple sources may be accommodated, but multiple sinks may not.Arc capacities must be the same in either direction.There are several different linear programming formulations for the model.The connected arcs may contain no cycles.2. Question : A PERT/CPM network can be represented as a linear programming model by letting the decision variables be the activity start times.TrueFalse3. Question : Which of the following is true about an intermediate node in a transshipment problem?The net flow out must be zero.The node must connect to at least one supply node and at least one demand node.The number of arcs connected to supply nodes must be less than or equal to the number of arcs connected to demand nodes.The total capacity of outbound arcs must equal the total capacity of inbound arcs.4. Question : Any attempt at resource leveling always will involve lengthening the project completion time beyond its “non-leveled” minimum.TrueFalse5. Question : Minimal spanning tree problems do not lend themselves to a convenient linear programming formulation. (True, medium)TrueFalse6. Question : A B-1 bomber must fly through a choice of “safe areas,” deliver its bombing payload, and return to its home base using minimum fuel. Which network model would be the most appropriate representation?Shortest pathMinimal spanning treeTraveling salesmanTransportation7. Question : In which of the following network models is it not possible to “ship” both in and out of a given node?TransshipmentTraveling salesmanMaximal flowAssignment8. Question : An environmental impact report for a proposed new industrial center complex must include the total amount of sewage that can be pumped through existing pipes. Which network model would be the most appropriate representation?Shortest pathMinimal spanning treeTraveling salesmanMaximal flow9. Question : You can solve the traveling salesman problem by selecting a cycle with the lowest cost.TrueFalse10. Question : Using the Critical Path Method, the normal time to complete activity D is 10 weeks, and its normal cost is $500. Under maximum crashing, activity D can be completed is 4 weeks for $2,300. Therefore, if $1,100 is spent on activity D, its completion time will be 6 weeks.TrueFalse 
http://www.ashfordhomeworks.com/download/bus-461-week-3-quiz/
Get more answer for your homework and exam at www.ashfordhomeworks.com
Download more answer at www.ashfordhomeworks.com
Download exams at http://www.ashfordhomeworks.com/download/bus-461-week-3-quiz/
1. Question : In a maximal flow problem:Multiple sources may be accommodated, but multiple sinks may not.Arc capacities must be the same in either direction.There are several different linear programming formulations for the model.The connected arcs may contain no cycles.2. Question : A PERT/CPM network can be represented as a linear programming model by letting the decision variables be the activity start times.TrueFalse3. Question : Which of the following is true about an intermediate node in a transshipment problem?The net flow out must be zero.The node must connect to at least one supply node and at least one demand node.The number of arcs connected to supply nodes must be less than or equal to the number of arcs connected to demand nodes.The total capacity of outbound arcs must equal the total capacity of inbound arcs.4. Question : Any attempt at resource leveling always will involve lengthening the project completion time beyond its “non-leveled” minimum.TrueFalse5. Question : Minimal spanning tree problems do not lend themselves to a convenient linear programming formulation. (True, medium)TrueFalse6. Question : A B-1 bomber must fly through a choice of “safe areas,” deliver its bombing payload, and return to its home base using minimum fuel. Which network model would be the most appropriate representation?Shortest pathMinimal spanning treeTraveling salesmanTransportation7. Question : In which of the following network models is it not possible to “ship” both in and out of a given node?TransshipmentTraveling salesmanMaximal flowAssignment8. Question : An environmental impact report for a proposed new industrial center complex must include the total amount of sewage that can be pumped through existing pipes. Which network model would be the most appropriate representation?Shortest pathMinimal spanning treeTraveling salesmanMaximal flow9. Question : You can solve the traveling salesman problem by selecting a cycle with the lowest cost.TrueFalse10. Question : Using the Critical Path Method, the normal time to complete activity D is 10 weeks, and its normal cost is $500. Under maximum crashing, activity D can be completed is 4 weeks for $2,300. Therefore, if $1,100 is spent on activity D, its completion time will be 6 weeks.TrueFalse 
http://www.ashfordhomeworks.com/download/bus-461-week-3-quiz/Download answer at http://www.ashfordhomeworks.com/download/bus-461-week-3-quiz/
1. Question : In a maximal flow problem:Multiple sources may be accommodated, but multiple sinks may not.Arc capacities must be the same in either direction.There are several different linear programming formulations for the model.The connected arcs may contain no cycles.2. Question : A PERT/CPM network can be represented as a linear programming model by letting the decision variables be the activity start times.TrueFalse3. Question : Which of the following is true about an intermediate node in a transshipment problem?The net flow out must be zero.The node must connect to at least one supply node and at least one demand node.The number of arcs connected to supply nodes must be less than or equal to the number of arcs connected to demand nodes.The total capacity of outbound arcs must equal the total capacity of inbound arcs.4. Question : Any attempt at resource leveling always will involve lengthening the project completion time beyond its “non-leveled” minimum.TrueFalse5. Question : Minimal spanning tree problems do not lend themselves to a convenient linear programming formulation. (True, medium)TrueFalse6. Question : A B-1 bomber must fly through a choice of “safe areas,” deliver its bombing payload, and return to its home base using minimum fuel. Which network model would be the most appropriate representation?Shortest pathMinimal spanning treeTraveling salesmanTransportation7. Question : In which of the following network models is it not possible to “ship” both in and out of a given node?TransshipmentTraveling salesmanMaximal flowAssignment8. Question : An environmental impact report for a proposed new industrial center complex must include the total amount of sewage that can be pumped through existing pipes. Which network model would be the most appropriate representation?Shortest pathMinimal spanning treeTraveling salesmanMaximal flow9. Question : You can solve the traveling salesman problem by selecting a cycle with the lowest cost.TrueFalse10. Question : Using the Critical Path Method, the normal time to complete activity D is 10 weeks, and its normal cost is $500. Under maximum crashing, activity D can be completed is 4 weeks for $2,300. Therefore, if $1,100 is spent on activity D, its completion time will be 6 weeks.TrueFalse 
http://www.ashfordhomeworks.com/download/bus-461-week-3-quiz/