• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/3

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

3 Cards in this Set

  • Front
  • Back
Explain how to convert a project plan into a project budget
The Gantt Chart shows what activities you will do, when they
will be done and how long they will last
<
If you know how much time and how many materials you need
you can estimate the project budget
Describe the major costs associated with a biotechnology project and the risks and benefits of attempting to reduce those costs
It is often easiest (and reasonable) to estimate costs based on
researcher time.

Costs depend on actual activities but it is reasonable to assume that for
a molecular biology / protein chemistry lab in a product development
setting:

Lab costs of $46,000 per researcher per year = $200 per day
<
Office-based costs of $11,500 per person per year = $50 per day
<
Examples of other costs to be considered:
<
Travel
<
Conferences
<
Training
<
Patents
<
Consultants
-
?