6 Cards in this Set

  • Front
  • Back
Which Requirements Management and Communication task may seek approval and sign-off on the communicated requirements?

a. Obtain requirements sign-off
b. Communicate requirements
c. Conduct requirements review
d. Create requirements package
b. Communicate requirements
What stakeholder is responsible and accountable for the project scope?

a. Project sponsor
b. Business analyst
c. Project manager
d. Process owner
c. Project manager
The performance of the Requirements Management and Communication tasks is governed by which plan?

a. Requirements Management plan
b. Project Management plan
c. Business analysis plan
d. Configuration management plan
c. Business analysis plan
Which statement is TRUE about communicating requirements?

a. Requirements must be verified and validated in order to be communicated.
b. Requirements must be formally distributed, reviewed and agreed upon.
c. Requirements must be traced and reusable prior to be communicated.
d. Requirements may be communicated without using a requirements package.
d. Requirements may be communicated without using a requirements package.
An email message is sent to project stakeholders with a graphical model subset of the solution requirements attached to the message. This is an example of what type of requirements presentation format?

a. Informal
b. Targeted
c. Formal
d. Virtual
a. Informal
You are a business analyst tasked with ensuring that stakeholders with approval authority agree about the requirements that the solution should meet. You are most likely performing tasks from which knowledge area?

a. Business Analysis Planning and Monitoring
b. Entreprise Analysis
c. Requirements Management and Communication
d. Solution Assessments an Validation
c. Requirements Management and Communication