7 Cards in this Set

  • Front
  • Back

Ammonia to the pre neutralizer is used in what form

Vapor

Ammonia to the XYZ granulator is used in what form

vapor

described the set up procedure for the pre neutralizer ammonia system

1.Have the operator set back pressure to 50PSI


2.close all drains, remove all open tags, complete ammonia drain checklist


3.fill abatement sump &


start abatement pump


4.verify abatement water bypass valves at the vaporizers are closed


5.verify manual back pressure valve is open


6.verify chiller bypass line is closed


7.verify granulator vaporizer bypass line is closed


8.verify ammonia relief valves are srt up correctly


9.close steam block valve to pren. sparges


10.verify chiller is set up correctly


11.verify abatement pump pressure is sufficient


12.set up 1" return line to ammonia header


13.slowly open main ammonia block valve


14.inspect entire system for leaks


what is the purpose of the 1" relief line from the vaporizers that go back to the ammonia feed supply line

in the event of an overpressure of the vaporizer this line relieves excessive pressure back to the main ammonia header and prevents the relief valve from lifting at the vaporizers preventing a release to the atmosphere

describe the procedure for bleeding down the ammonia system to the pre neutralizer and the granulator

1.ensure drain tanks and ditches have enough water


2.inspect bottom of drain lines to make sure there is no blockages


3.close Double block valves and open bleed line


4.open drains and hang open tags


5.manually open back pressure valve


6.check system to make sure is at "0" pressure

If the feed ends of the scalping screens are plugged with lumps you would expect to

Go into oversize

if scrap metal enters the system through the scrap relcaim elevator you would expect to find the metal

In the lump crusher