94 Cards in this Set
- Front
- Back
write ________ ________ ___ instructions to clarify who does what
|
subcontract general bid
|
|
write ________ _____ _________
|
subcontract trade instructions
|
|
require the subcontractors to submit their bids on a standard __________ _______ _____
|
subcontractor proposal form
|
|
request a _________ form from the subs
|
pre-qualification
|
|
require a ___ ________ form to be submitted
|
bid breakdown
|
|
place a ____ _____ on bid submittals
|
time limit
|
|
subcontract bid instructions- include all costs for:
|
fees
meters permits |
|
any wording on the plans, specs, or other bid documents referring to material to be furnished by General contractor, tenant's general contractor, tenants contractor, should be interpreted to mean:
"by __________ responsible for the type of work involved" |
subcontractor
|
|
guarantee all materials and workmanship for at least _____ from the time of ________
|
1 year
completion |
|
material / equipment:
where __ ______ is stated, you will be allowed to substitute, providing you are able to prove to the owner or their agent that the selection is of equal quality, capacity, and design to that specified |
or equal
|
|
who is bound to all labor agreements
|
subcontractor
|
|
by submission of the bid you acknowledge that you are familiar with ___ ____ and should your investigations contradict that then you will not be relieved from _______ the work as shown or required
|
the site
completing |
|
any proposed substitution must have the approval of
|
the owner's representative
|
|
if allowances are indicated in the specs then should you include them in your bid?
|
yes, with amount included
|
|
material or equipment that has not been paid for is a
|
pre-ordered item
|
|
should you include the cost of pre-ordered items in your bid
|
yes
|
|
should you include the cost of materials furnished by other people
|
yes
|
|
cutting, framing, and patching of all required openings must be done by the
|
subcontractor
|
|
the exception to the cutting, framing, and patching done by the subcontractor is...
|
drywall contractors must cut and frame all necessary openings in drywall CEILINGS
|
|
who is the only person that may perform work that will penetrate the roof
|
developer's roofing contractor
|
|
who is required to clean the premises once a day
|
subcontractors performing work
|
|
if equipment, materials, or supplies are furnished by others, it will be the responsibility of the _________ who installs the items to clean up and dispose of debris
|
subcontractor
|
|
should costs for unloading be included
|
yes
|
|
should costs for excavating necessary to install any under slab mechanical or electrical material be included?
|
yes
|
|
subs are required to attend the ________ meeting to approve the master schedule and attend all _______ meetings
|
preconstruction
planning |
|
each _________ must submit a material status report _______
|
subcontractor
monthly |
|
renewal certificates shall be submitted at least __ days prior to ________
|
4 days
expiration |
|
all subs must file an insurance certificate for comprehensive general liability and automobile liability insurance in the amount specified in the contract docs prior to ________ _____
|
commencing work
|
|
all subs must submit workers compensation guaranteed prior to
|
commencing work
|
|
shop drawings and product data must be submitted to the
|
general contractor
|
|
the subcontract agreement is completed after the signing by the
|
owner and GC
|
|
the subcontract agreement is prepared by the
|
GC
|
|
the subcontract agreement is sent to the
|
Subcontractor
|
|
the subcontract signed agreement between the parties is called the
|
meeting of the minds
|
|
after the contractor has received a owner/contractor agreement, they will notify the subcontractor using a
|
notice of award
|
|
after the signing of the subcontract agreement the sub must submit
|
insurance certificates
|
|
what forms are needed to organize the subcontractors bids (5)
|
bid instructions
bid breakdown bid comparison trade instructions agreement |
|
the subcontract general bid instructions clarify who
|
does what
|
|
what clarifies who furnishes and or installs specific materials, equipment, fees, and services
|
subcontract general bid instructions
|
|
examples of who does what (what is done)
|
cleanup
unloading excavation demolition etc. |
|
subcontract general bid instructions or AIA general conditions:
bonds, permits, fees liscensed to complete work items furnished by others labor agreements cleanup unloading proposal form |
subcontract general bid instructions
|
|
subcontract general bid instructions or AIA general conditions:
party responsibilities claims procedures change procedures safety procedures submittal procedures termination procedures |
AIA
|
|
subcontract bid breakdown and proposal form:
price breakdown by systems or |
location
|
|
subcontract bid breakdown and proposal form:
total price in |
numbers and written
|
|
subcontract bid breakdown and proposal form:
prevailing wages table by ______ and ____ |
county and date
|
|
subcontractor agreement parties
|
contractor
subcontractor owner A/E |
|
subcontract agreement:
stated name and document along with how many criteria? |
4
|
|
subcontract agreement:
scope description- addresses how many content areas |
5
|
|
general bid inclusions
specific trade activities systems or locations complete and operational accepted by the owner these are the what |
5 content areas
|
|
CRSI, ACI, NEC, ASTM, OSHA, must be contained in the
|
subcontractor agreement
|
|
procurement process:
prepare _____ list |
want
|
|
procurement process:
request ____ _________ |
price quotations
|
|
procurement process:
write _____ ____ |
purchase order
|
|
procurement process:
_______ materials |
expedite
|
|
procurement process:
_______ shipment of materials |
arrange
|
|
procurement process:
check ______ list |
packing
|
|
the want list is sent from the _______ ________ to ________
|
construction dept
purchasing |
|
the request for price quotations is from the ________
|
contractor
|
|
the purchase order is from the _______ to the _______
|
contractor
vendor |
|
who expedites the materials
|
contractors purchasing dept
|
|
"arrange shipment of materials" is from the _______ to the _______
|
vendor
jobsite |
|
"check packing list" is from
|
contractors field personnel
|
|
the billing document from the supplier requesting payment for materials
|
invoice
|
|
the vendor is only responsible for loading the order on the shippers vehicle at the factory (shipping term)
|
FOB factory
|
|
means that the vendor is responsible for loading your order on the shipper's vehicle at the sales location and ownership transfers from the supplier to the buyer at the sales location (shipping term)
|
FOB suppliers sales
|
|
the shipping document is known as
|
bill of lading
|
|
contractual agreement between the shipper and a common carrier to move the material from location A to location B for a specified price (shipping term)
|
bill of lading
|
|
if the shipping terms are FOB factory, the bill of lading is between the common carrier and the
|
buyer
|
|
if the shipping terms are FOB jobsite, the bill of lading is between the common carrier and the
|
supplier
|
|
CIF
|
cost plus insurance and freight
|
|
shipping term COD
|
cost on delivery
|
|
accounting term ROG
|
receipt of goods
|
|
accounting term:
this means that a 1% discount can be deducted from the purchase order amount if the contractor pays within 10 days or receipt of goods ROG. The full payment is due in 30 days |
1/10 NET 30
|
|
accounting term:
this means a 1% discount can be deducted from the purchase order amount if the contractor pays before the eleventh of the month following receipt of goods (ROG). The full payment is due thereafter |
1/10 EOM
|
|
EOM
|
eleventh of the month
|
|
accounting term:
this means a 1% discount can be deducted if payment is made within 10 days of the invoice date. The full payment is due in 30 days |
1/10 PROX 30
|
|
accounting term:
_______ receives the original to confirm the order prices, quantities and terms |
vendor
|
|
accounting term:
________ ______ keeps a copy for reference and purchase order numbers used |
purchasing agent
|
|
accounting term:
________ will receive a copy if they had requested materials using a purchase requisition. The purchase order would be sent to confirm the orders had been placed |
originator
|
|
accounting term:
accounts payable will receive a copy to compare quantities, items and unit prices with the invoice before making payment |
accounting
|
|
accounting term:
________ will receive a copy to compare the quantities and items shipped |
receiving
|
|
accounting term:
________ receives a copy for following up orders to ensure that the correct documentation and materials arrive according to the scheduled delivery dates |
expediting
|
|
purchase order or purchase order change?
0921 |
purchase order
|
|
purchase order or purchase order change?
0921-04 |
purchase order change
|
|
the process of following up on materials and vendor submittals to ensure that the proper materials and quantities are in compliance with the specifications and they arrive as scheduled. The person performing this function is sometimes called an expiditor.
|
expediting materials
|
|
the amount of time required by vendors to deliver materials to the jobsite. When determining the amount of time required to deliver materials, the following steps must be reviewed to determine the amount of ________ required for an item
|
leadtime
|
|
a want list is also called a
|
purchase requisition
|
|
requisitions are used for
|
controlling materials internally
|
|
what law does a purchase order fall under
|
Uniform commercial code
|
|
UCC
|
uniform commercial code
|
|
the process of following up on materials and submittals
|
expediting
|
|
FOB factory - ________ responsibility after loaded at factory
|
contractors
|
|
FOB sales office - _________ responsibility after loaded at retailers
|
contractors
|
|
FOB jobsite - _______ responsibility until after unloaded at site
|
vendors
|