the overlapping accomplishment of Design, Procurement, and Construction activities to complete a project faster
|
fast tracking
|
|
the shortening of the project schedule along the critical path using the activities on the critical path with the least cost. No activity can be crashed to a zero duration
|
crashing
|
|
the shifting of activities within the schedule using the free floats times available
|
resource leveling
|
|
the total amount of time required to receive approved materials on the jobsite
|
leadtime
|
|
lead time report consists of: (3)
|
bid time
prepared shop drawings on time shipment |
|
the time required by the vendor to prepare inquiry and mail bid
|
bid time
|
|
the time required after receipt of contract to prepare and mail shop drawings
|
prepare shop drawings time
|
|
the time from receipt of complete drawing approvals plus the time needed to fabricate the item
|
shipment
|