94 Cards in this Set
- Front
- Back
Where do you go to get construction product info
|
sweet's catalog
|
|
where do you go to get info on manufacturers technical data
|
thomas' register
|
|
how do you get the total "N" blow count?
|
add counts 2 and 3
|
|
which term distinguishes shop drawings from product data sheets
|
isometrics or assembly plans
|
|
who is the primary developer of shop drawings
|
subcontractor or vendor
|
|
who reviews and approves all shop drawings
|
field engineer
|
|
who reviews and approves all shop drawing submittals
|
architect
|
|
what is the name of the document that the contractor must use to inform the A/E of a change to the shop drawing
|
letter of transmittal
|
|
what is the position that typically develops and maintains the shop drawing submittal logs
|
field engineer
|
|
the document that tells the contractor the specific shop drawings, product data sheets, and samples that are required
|
part 1 of each section of a technical description division
|
|
who is responsible for dewatering requirements
|
contractor
|
|
who is responsible for formwork design
|
field engineer
|
|
aace
|
association for the advancement of cost engineering
|
|
abc
|
associated builders and contractors
|
|
agc
|
associated general contractors
|
|
aic
|
american institute of constructors
|
|
apam
|
asphalt pavement association of michigan
|
|
asa
|
american subcontractors association
|
|
aspe
|
american society of professional estimators
|
|
asse
|
american society of safety engineers
|
|
cam
|
construction association of michigan
|
|
cfma
|
construction financial management association
|
|
cmaa
|
construction management association of america
|
|
csi
|
construction specifications institute
|
|
mita
|
michigan infastructure and transportation association
|
|
nahb
|
national association of home builders
|
|
namc
|
national association of minority contractors
|
|
nawic
|
national association of women in construction
|
|
pmi
|
project management institute
|
|
who must provide documentation to the contractor that proves the DBE, MBE and WBE are registered
|
subcontractor
|
|
document that specifies the regulatory goals for mbe, wbe, and dbe contractors
|
general requirements
|
|
which document is the definition of days in
|
GC
|
|
what does the term "day" mean
|
calendar days, unless otherwise specified
|
|
which document specifies the number of days to execute the contract - title
|
ITB - Time for executing the contract
|
|
how many days do you have to provide the contract bonds and from what period
|
14 days from notice of award
|
|
what is the consequence if the contract bond is not provided
|
owner keeps proposal guarantee money
|
|
what are the three documents that must be provided at the signing of the contract
|
performance bond
payment bond certificate of insurance |
|
name of title for document that specifies procedures when encountering hazardous material, PCB, or asbestos
|
Hazardous materials
|
|
who is the responsible for notifying if hazardous materials are encountered
|
contractor has to notify
|
|
what are the procedures if hazardous materials are encountered
|
-notify the owner orally and in writing
-stop work in the affected area |
|
what are the consequences if the contractor disturbs the hazardous material before notifying the owner
|
contractor is responsible for disposing of the materials at their own expense
|
|
title of document which specifies regulatory requirements for soil erosion
|
Soil Erosion and Sedimentation
|
|
what soil erosion act must the contractor comply with
|
Act 347, 1972 Amendment
|
|
when is a soil erosion control permit required
|
within 500 feet of any body of water
|
|
title of document which specifies the time limit for requesting a claim or change
|
Notice of Claims
|
|
how many days do you have to request a claim or change and from what point in time
|
21 days from first occurrence
|
|
title that deals with requesting weather time extension
|
claims time
|
|
consequences if you dont submit schedule of values and construction schedule
|
first payment is withheld
|
|
how many days do you have to submit the construction schedule and from which point in time
|
14 days from notice of award
|
|
title that corresponds to the document which specifies the payment request due date
|
Application for payment
|
|
what is the payment request due date
|
on or before the 25th day of the month
|
|
title of the document which specifies the payment due date from the owner
|
applications for payment
|
|
what is the payment due date from the owner
|
by the 5th of the following month
|
|
title of document which specifies retainage percentage
|
application for payment
|
|
what is the retainage percentage amount
|
5%
|
|
what is the title of the document which corresponds to liquidated damages
|
substantial completion
|
|
what is the liquidated damages amount?
|
1200/day
|
|
what is the title of the document which corresponds to the steps the contractor must take if the owner fails to pay
|
failure of payment
|
|
the procedure if the owner fails to pay is for the contractor to within ____ days, submit a notice of intent to stop work
|
7
|
|
after submitting a notice of intent to stop work, the contractor must continue working for ____ additional days
|
7
|
|
the form the contractor fills out if the owner fails to pay is referred to as
|
a stop work notice
|
|
what is the title of the document which corresponds to itemized cost items on a change order proposal
|
contract change order
|
|
which party submits the itemized quotation on the change order
|
contractor
|
|
labor, equipment, material, consumable supplies are indirect or direct cost items
|
direct
|
|
workers comp, unemployment, social security, sales tax, bond premium are indirect of direct cost items
|
indirect
|
|
what is the percentage that can be charged for overhead and profit?
|
15%
|
|
how many copies of shop drawings must be on site
|
the number the contractor requires plus an additional 2 copies for the A/E
|
|
how many copies of manufacturers instructions must be on site
|
the number the contractor requires plus an additional 2 copies for the A/E
|
|
which parties can initiate a Change Order request
|
contractor
owner |
|
a change after the signing of the contract is a ___________
|
change order
|
|
a change order states changes in the...
|
work, sum, and time
|
|
which section do you look in if youre looking for info on a bid procedure
|
Instructions to Bidders
|
|
which section do you look in if youre looking for info on a contractual constant
|
general conditions
|
|
which section do you look in if youre looking for info on a contractual cost item that is job specific
|
supplementary conditions
|
|
which section do you look in if youre looking for info on a specific administrative of procedural cost item
|
general requirements
|
|
what is the title that corresponds to a document which states the time frame for submitting a claim
|
claims and disputes
|
|
what is the time frame for submitting a claim and from what point in time
|
21 days from first occurrence
|
|
which party develops a change order proposal and submits
|
contractor
|
|
notice of award means that
|
youve won the bid
|
|
obtain the contract bond within
|
14 days
|
|
what is the name of the form from the owner that grants the contractor permission to occupy the job site
|
notice to proceed
|
|
the notice to proceed means that you have the ability to...
|
get on the job site
|
|
which form establishes the start date of the project
|
notice to proceed
|
|
which party issues the stop work order
|
owner
|
|
who do orders always come from
|
the owner
|
|
25th of the month
|
request for payment
|
|
5th of the month
|
payment is due
|
|
what is the page abbreviation and the number of pages for the ACTUAL schedule of values
|
PMF pages 1-6
|
|
which party submits the construction schedule
|
contractor
|
|
which party maintains a record copy of the as-built drawings
|
contractor
|
|
who will the marked up, record copies be delivered to and when
|
delivered to the owner upon completion of the work
|
|
completion of the work is also referred to as...
|
substantial completion
|
|
which party will make and distribute the punch list
|
A/E
|
|
which party completes the certificate of substantial completion
|
A/E
|