EXPANSION/ISOLATION JOINT
|
Seperates a slab from other parts of a structure and permit it to move horizontally and vertically.
|
|
What is the minimum clearance between parallel rebars?
|
2.5"
|
|
Where should the shotcrete process begin?
|
COVE
|
|
What should be done with any rebound during shotcrete application?
|
DISREGARD - DO NOT USE
|
|
How long should concrete remain moist after application?
|
7 DAYS
|
|
What is considered "cold"?
|
More than 3 consecutive days: