• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/131

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

131 Cards in this Set

  • Front
  • Back
  • 3rd side (hint)

What does PV stand for?

Planned Value

also known as BCWS (Budgeted Cost of Work Scheduled)

How is PV defined?

The value of the work planned to be completed TO A POINT IN TIME.



how much you think you will have to spend to get to a certain point

What does EV stand for?

Earned Value

also known as BCWP (Budgeted Cost of Work Performed)

How is EV defined?

The planned value (PV) of all the work completed (earned) TO A POINT IN TIME, without reference to actual costs.

how much you thought you would have to spend by this point

What does AC stand for?

Actual Cost

also known as ACWP (Actual Cost of Work Performed)

How is AC defined?

The actual cost of all the work completed to a point in time.

in reality...

What does BAC stand for?

Budget at Completion


How is BAC defined?

The value of total planned work, or, the project cost baseline.

The v. of t.p.w., or, the p.c.b.

What does CV stand for?

Cost Variance


How is CV calculated?

CV = EV - AC

what you thought it would cost to get to this point - what it actually ended up costing

If your calculated CV value is greater than 1, what does that mean?

You are under your planned cost.

CV = EV - AC

If your calculated CV value is less than 1, what does that mean?

You are over your planned cost.

CV = EV - AC

What does SV stand for?

Schedule Variance

How is SV calculated?

SV = EV - PV

it doesn't make sense - just memorize it

If your calculated SV value is greater than 1, what does it mean?

You are ahead of schedule.

SV = EV - PV

If your calculated SV value is less than 1, what does it mean?

You are behind schedule.

SV = EV - PV

What does VAC stand for?

Variance at Completion

How is VAC calculated?

VAC = BAC - EAC

If your calculated VAC is greater than 1, what does it mean?

You are under your planned cost.

VAC = BAC - EAC

If your calculated VAC is less than 1, what does it mean?

You are over your planned cost.

VAC = BAC - EAC

What does CPI stand for?

Cost Performance Index

How is CPI defined?

It is a measure of the cost efficiency of budgeted resources

It is a m. of the c.e. of b.r.

How is CPI calculated?

CPI = EV / AC

it's a ratio...

If your calculated CPI is greater than 1, what does it mean?

You are under planned costs.

CPI = EV / AC

What does it mean if your calculated CPI is less than 1?

You are over your planned costs.

CPI = EV / AC

What does SPI stand for?

Schedule Performance Index

How is SPI defined?

It is a measure of schedule efficiency.

It is a m. of s.e.

How is SPI calculated?

SPI = EV / PV

"An SPI of 1.0 means the project is exactly on schedule, that the work actually done so far is exactly the same as the work planned to be done so far."

What does it mean if your SPI is greater than 1?

You are ahead of schedule.

SPI = EV / PV

What does it mean if your SPI is less than 1?

You are behind schedule.

SPI = EV / PV

What does EAC stand for?

Estimate at Completion

How is EAC defined?

The expected total cost of completing all work.

The e.t.c. of c.ing a.w.

How is EAC calculated if the future work will be accomplished at the planned rate?

EAC = AC + BAC - EV

AC = how much it has actually cost to get to this point


EV = how much it was supposed to cost to get to this point


BAC = how much it is supposed to cost to complete the project

What is the difference between PV and EV?

PV is the budgeted cost of work SCHEDULED; EV is the budgeted cost of work COMPLETED.

PV = b.c. of w. S.


EV = b.c. of w. C.



How is EAC calculated if the CPI is expected to be the same for the remainder of the project?

EAC = BAC / CPI

The CPI is a ratio - this applies the ratio to the entire BAC.

How is EAC calculated if the initial plan is no longer valid?

EAC = AC + Bottom-Up ETC

start over...

What does ETC stand for?

Estimate to Complete

How is ETC defined?

The expected cost to finish all the remaining project work.

The e.c. to f. all the r.p.w.

If work is proceeding on plan, how do you calculate ETC?

ETC = EAC - AC

how much you think you will spend in total - how much you've actually already spent

What is the difference between BAC and EAC?

BAC is your original projected budget, the project cost baseline. It does not change over time.


EAC is your estimate of the total project cost, updated as the project advances.

original v updated

What does VAC stand for?

Variance at Completion


How is VAC defined?

A projection of the amount of budget surplus or deficit.

A p. of the a. of b.s. or d.

How is VAC calculated?

VAC = BAC - EAC

original - updated

What does it mean if your VAC is greater than 1?

You are estimating that you will be under budget at the completion of the project.

VAC = BAC - EAC

What does it mean if your VAC is less than 1?

You are estimating that you will be over budget at the completion of the project.

VAC = BAC - EAC

What does TCPI stand for?

To Complete Performance Index

How is TCPI defined?

It is a measure of the cost performance that must be achieved with the remaining resources in order to meet a specified management goal.

It is a m. of the c.p. that must be a. with the r.r. in o.t.m. a s.m.g.

How do you calculate TCPI in order to complete a project on the original plan?

TCPI = (BAC - EV) / (BAC - AC)


How do you calculate TCPI in order to complete a project within your EAC?

TCPI = (BAC - EV) / (EAC - AC)

What does it mean if your TCPI is greater than 1?

It will be harder to complete your project on plan or within the EAC.

What does it mean if your TCPI is less than 1?

It will be easier to complete your project on plan or within the EAC.

What does PERT stand for?

Program Evaluation and Review Technique

it is a Activity on Node (AON) method

What is the formula for the PERT mean?

PERT mean = (P + 4L + O) / 6

pessimistic, likely, optimistic

What is the formula for the PERT standard deviation?

PERT S.D. = (P - O) / 6

pessimistic, optimistic

How is decomposition defined?

A technique used for dividing and subdividing the project scope and project deliverables into smaller, more manageable parts.

decomposition breaks things down...
In which organizational structure do project managers have the most authority?

Projectized


What are the three main types of organizational structures?

Functional, Matrix, and Projectized


Matrix organizations are a blend of what two types of organizations?

Functional and Projectized


Which of the following is NOT an example of an organizational process asset:


a. lessons learned


b. completed schedules


c. rules and laws


d. WBS templates




c. rules and laws


Organizational process assets are the plans, processes, policies, procedures, and knowledge bases specific to and used by the performing organization



What are the two types of organizational process assets?


processes and procedures


AND


corporate knowledge base


p. and p.


AND


c.k.b.


Who are the project stakeholders?

Project stakeholders include all members of the project team as well as all interested entities that are internal or external to the organization.

team + internal + external

When is stakeholder identification performed?

Stakeholder identification is a continuous process throughout the entire project life cycle.

What does PMO stand for?

Project Management Office


What are the four phases of the generic project life cycle?


Starting the project


Organizing and preparing


Carrying out the work


Closing the project


What are the five project management process groups?

Initiating Process Group


Planning Process Group


Executing Process Group


Monitoring and Controlling Process Group


Closing Process Group


What is a Pareto diagram?

A special form of a vertical bar chart that are used to identify the sources that are responsible for causing most of a problem's effects.


What are two other names for cause-and-effect diagrams?

Fishbone diagrams


AND


Ishikawa diagrams



What is the basic structure of a fishbone diagram?


Head: problem statement


Bones: Why did this happen?


Continue asking why


What are control charts used for?
To determine whether or not a process is stable or has predictable performance.

When is a process considered out of control?


1. a data point exceeds a control limit


2. 7 consecutive plot points are above the mean


3. 7 consecutive plot points are below the mean






What is benchmarking?

Benchmarking involves comparing actual or planned project practices to those of comparable projects to identify best practices, generate ideas for improvement, and provide a basis for measuring performance.






_____ is the process of monitoring the status of the project to update the project process and manage changes to the schedule baseline:


1. Control Schedule


2. Schedule Analysis


3. Define Schedule Assumptions


4. Schedule Updating Process






1. Control Schedule

What are the seven basic quality tools (7QC Tools)?

Ishikawa diagrams


flowcharts


checksheets


Pareto diagrams


histograms


control charts


scatter diagrams


What is a force field analysis?
A quality planning tool that diagrams forces for and against change.


What are the five outputs of the Plan Quality Management process?

Quality Management Plan


Process Improvement Plan


Quality Metrics


Quality Checklists


Project Documents Updates


The ___ technique allows large numbers of ideas to be sorted into groups for review and analysis:


1. Brainstorming


2. Nominal group


3. Idea/mind mapping


4. Affinity diagram





4. Affinity diagram

When is a deliverable considered an accepted deliverable?
When it meets all acceptance criteria and has been formally signed off and accepted by the customer or sponsor.

2 conditions...

What is the critical chain method?

It is a schedule method that allows the project team to place buffers on any project schedule path to account for limited resources and project uncertainties.





What is a project buffer?

A buffer placed at the end of the critical chain to protect the target finish date.

What is a feeding buffer?

A buffer placed at a point where a chain of dependent activities that are NOT on the critical chain feed into the critical chain.

side bar...
How is crashing defined?
Crashing is a technique used to shorten the schedule duration for the least incremental cost by adding resources.

How is fast tracking defined?

Fast tracking is a schedule compression technique in which activities or phases normally done in sequence are performed in parallel for at least a portion of their duration.


What is the schedule baseline.

It is an output of the Develop Schedule process, and is the approved version of a schedule model that can be changed only through formal change control procedures.

What is resource leveling?


A resource optimization technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply.








What is the formula for the total number of potential communication channels?

C = (n*(n-1))/2

What information should be included in a business case?
The necessary information from a business standpoint to determine whether the project is worth the investment.

What should be included in a requirements management plan?
It should describe how requirements activities will be planned, tracked, and reported.
You're managing something...
What is an AOA network diagram?

Activity on Arrow


What is an AON network diagram?

Activity on Node

What is the Delphi technique?

An information gathering technique used to reach a consensus of experts on a subject without letting one person dominate the discussion. It uses an anonymous questionnaire and recirculation.





the Oracle was an expert...
What is the critical path?

The critical path is the sequence of activities that makes the longest path through a project, which determines the shortest possible project duration.




What is total float?

The amount of time that a schedule activity can be delayed or extended for its early start date without delaying the project finish date or violating a schedule constraint.




measures schedule flexibility...
What is a synonym for float?

slack

A customer needs you to set up a booth for an upcoming exhibition on November 1. It is now September 1. It will take four days to set up the booth. What is the project float?

60 days - 4 days = 56 days


What are the TWO formulas to calculate total float?

TF = Late start - early start


OR


TF = Late finish - early finish


late first...
What is the formula for calculating free float?

FF = Early start of next activity - early finish of current activity - 1
involves 2 activities...

How much float do activities on the critical path have?

zero - no free float, no total float

they sink...
What are the five stages of team development in the Tuckman ladder?

Forming


Storming


Norming


Performing


Adjourning/Mourning


they rhyme!
What are "soft skills"?

Interpersonal skills - communication skills, emotional intelligence, conflict resolution, etc.

What does QFD stand for?
Quality Function Deployment


What is a QFD?
A QFD is a facilitated workshop technique that helps determine critical characteristics for new product development.

A QFD is a f.w.t. that helps d.c.c. for n.p.d...

What three things can be included in schedule data?


Resource histograms


Cash-flow projections


Activity attributes


What is the most commonly used contract type?

Firm Fixed Price

f.f.p.
What does WBS stand for?

Work Breakdown Structure

What are JAD sessions?
Joint application development sessions focus on bringing users and the development team together to improve the software development process.

Which of the following tools & techniques in Estimate Activity Durations is considered to produce the most accurate estimate?


a. expert judgment


b. analogous estimating


c. parametric estimating


d. parabolic estimating






c. parametric estimating is considerd more accurate than analogous estimating

parabolic estimating isn't a thing...
What document details the steps for analyzing processes to identify activities and enhance their value?

Process Improvement Plan

What is a Product Scope?


The features and functions that characterize a product.

its catalog description...

What does RACI stand for?

Responsible


Accountable


Consulted


Inform



What does RACI refer to?
different tasks on a responsibility assignment matrix (RAM)

Contingency reserves are used to managed what type of risks?
Known risks


What are the "Triple Constraints"?

Scope, Time, Cost


What is the most accurate method of determining the project budget?

Bottom-up estimating

glug, glug...!

In Six Sigma, what percentage of accuracy is desired?

99.99966%


During which phase of the project will the risks be the highest?

Initiating

risk decrease as project proceeds...

In which project phase(s) do you identify project stakeholders?

All phases

iterative process...

What does the Project Charter do?

It formally authorizes the existence of the project & provides the PM with the authority to apply organizational resources to project activities


Can the Project Manager sign the Project Charter?

No.


Which matrix is most like a Functional organization structure?

Weak Matrix

In which matrix does the Project Manager have the most power?

Strong Matrix


Who manages the project budget in a Weak Matrix organization?

Functional Manager

In which matrix does the Project Manager have the most control over budget and resources?

Strong Matrix


What is analogous cost estimating?

Uses the values such as scope, cost, budget, and duration from a previous, similar project as the basis for estimating the same parameter or measurement for a current project.




When is analogous cost estimating often used?
Where there is a limited amount of detailed information about the project (eg, in early phases)

What is three-point estimating?

Making three estimates (most likely, optimistic, & pessimistic) to define an approximate range for an activity's cost


In three-point estimating, how do you calculate a triangular distribution?

Estimate = (P + L + O) / 3

In three-point estimating, how do you calculate a beta distribution?

Estimate = (P + 4L + 0) / 6

same as PERT mean....
What does EMV stand for?

Expected Monetary Value

What does SWOT stand for?

Strengths, Weaknesses, Opportunities, Threats


What is a SWOT analysis?


A technique that examines the project from each of the SWOT perspectives to increase the breadth of identified risks by including internally generated risks