• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/35

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

35 Cards in this Set

  • Front
  • Back
Priority order of Cost, Time, and Performance for CPFF is?
Cost, Time, Performance
Priority order of Cost, Time, and Performance for CPAF is?
Cost, Time, Performance
Priority order of Cost, Time, and Performance for CPIF is?
Time, Performance, Cost
Priority order of Cost, Time, and Performance for T&M is?
Performance, Time, Cost
Priority order of Cost, Time, and Performance for FPIF is?
Time, Performance, Cost
Priority order of Cost, Time, and Performance for FP is?
Cost, Time, Performance
What type of contract? You need work to begin right away
T&M
What type of contract? You want to buy expertise in determining what needs to be done
CR
What type of contract? You know exactly what needs to be done
FP
What type of contract? You are buying a programmers services to augment your staff
T&M
What type of contract? You need work done, but have time to audit the invoices
FP
What type of contract? You need to rebuild a bridge ASAP after a storm
FPIF
What type of contract? The project requires a high level of expertise to complete, and you want to have the best performance possible in a finished product
CPIF or CPAF
What type of contract? You need to hire a contractor to perform research and development
CR
What type of contract? The scope of work is complete, but the economy is currently unpredictable
FPEPA
What type of contract? You are buying a standard commodities
Purchase order
Cost Reimbursable, Time & Material, Fixed Price: Generally, what is being bought?
Cost Reimbursable: Service, goods may be included Time & Material: Service Fixed Price: Goods
Cost Reimbursable, Time & Material, Fixed Price: Describe how the costs to the buyer might be stated in the contract
Cost Reimbursable: Costs are variable, but the fee is fixed Time & Material: Hourly rate or price per unit Fixed Price: As a set currency amount
Cost Reimbursable, Time & Material, Fixed Price: Describe how the profit to the buyer might be stated in the contract
Cost Reimbursable: Listed separately and known to the buyer Time & Material: Included in the hourly rate and may be unknown to the buyer Fixed Price: Included in the price and unknown to the buyer
Cost Reimbursable, Time & Material, Fixed Price: What is the cost risk to the buyer? (High, Medium, or Low)
Cost Reimbursable: High - Increases in costs are reimbursed by the buyer Time & Material: Medium - the costs are not fixed, this contract type is used for small purchases Fixed Price: Low - increases in cost are born by the seller
Cost Reimbursable, Time & Material, Fixed Price: How important is a detailed SOW?
Cost Reimbursable: Low - the procurement SOW only needs to describe the performance or requirements since the seller provides the work. The buyer pays all costs, so there is less need to finalize the scope Time & Material: Low - this type traditionally has very little scope and may only describe skill sets required Fixed Price: High - the procurement SOW must be complete so the seller knows exactly what work needs to be done in order to come up with an accurate price to do the work
Cost Reimbursable, Time & Material, Fixed Price: What industry uses this most for its contracts?
Cost Reimbursable: IT, research, development - when the work has never been done before Time & Material: legal, plumbing, programming - when hiring for an hourly rate Fixed Price: construction - complete scope of work is needed
Cost Reimbursable, Time & Material, Fixed Price: How much negotiation is usually required to sign a contract after receipt of the seller's price? (High, Medium, or Low)
Cost Reimbursable: High - all estimated costs are looked at to calculate the fee to be fixed Time & Material: Low or none Fixed Price: None
Cost Reimbursable, Time & Material, Fixed Price: What level of effort and expertise will the buyer need to devote to managing the seller? (High, Medium, or Low)
Cost Reimbursable: High Time & Material: Medium Fixed Price: Low
Cost Reimbursable, Time & Material, Fixed Price: How are costs billed to the buyer?
Cost Reimbursable: Actual costs are incurred, profit at completion or apportioned, as allowed in the contract Time & Material: Hourly or per unit rate (which includes all costs and profit) Fixed Price: Fixed price (which includes profit) according to a payment schedule as work is competed and as allowed in the contract
Cost Reimbursable, Time & Material, Fixed Price: How much auditing of the seller's costs will the buyer need to do? (High, Medium, or Low)
Cost Reimbursable: High - all costs must be audited and there will be a large amount of costs Time & Material: None - there may be an audit of work hours completed against those billed, but that will take little effort Fixed Price: Low - since the overall contract costs are fixed, auditing usually focuses on making sure work is complete, not looking at detailed cost receipts
Which would win a dispute over contract interpretation: 1. Contract Language or 2. A memo by one of the parties describing proposed changes after the contract was signed
1. Contract Language
Which would win a dispute over contract interpretation: 1. Contract Language or 2. A memo signed by both parties before the contract is signed that describes what was agreed to during negotiations
1. Contract Language
Which would win a dispute over contract interpretation: 1. Contract terms & Conditions or 2. Procurement SOW
1. Contract terms & Conditions or 2. Procurement SOW
Which would win a dispute over contract interpretation: 1. Common definition or 2. The intended meaning (without supplying a definition)
1. Common definition
Which would win a dispute over contract interpretation: 1. Industry use of the term or 2. Common use of the term
1. Industry use of the term
Which would win a dispute over contract interpretation: 1. Special provision or 2. General provisions
1. Special provision
Which would win a dispute over contract interpretation: 1. Typed-over wording on the contract or 2. A handwritten comment on the contract that is also initialed
2. A handwritten comment on the contract that is also initialed
Which would win a dispute over contract interpretation: 1. Numbers or 2. Words
2. Words
Which would win a dispute over contract interpretation: 1. Detailed terms or 2. General terms
1. Detailed terms