• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/18

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

18 Cards in this Set

  • Front
  • Back

Plan HR Mgmt process

ID's and documents project roles, responsibilities, required skills, reporting relationships, and creating a staffing mgmt plan.

Plan HR Mgmt process inputs

1. PM Plan


1 from Develop PM Plan


2. Activity Resource Requirements


2 from Estimate Activity Resources


3 & 4. OPA's & EEF's

Info from the PM Plan that relates to Plan HR Mgmt Process

1. Project life cycle and the processes that will be applied to each phase.


2. How work will be executed to accomplish the project objectives


3 & 4. Change & Configuration Mgmt Plan


5. Maintaining the integrity of the baselines


6. Needs and methods of communicating with stakeholders.

Plan HR Mgmt process T&T's

1. Organizational Charts and Position Descriptions


2. Networking


3. Organizational Theory


4. EJ


5. Meetings

Three types of Organizational Charts and Position Descriptions

1. Hierarchical-type charts


2. Matrix-based charts


3. Text-oriented formats

Plan HR Mgmt process outputs

1. Roles and Responsibilities


2. Project Organization Charts


3. Staffing Mgmt Plan

What should be addressed when listing Roles and Responsibilities?

1. Role


2. Authority


3. Responsibility


4. Competency

Staffing Mgmt Plan is

a component of the HR Mgmt Plan that describes how and when project team members will be acquired and how long they will be needed.

Staffing Mgmt Plan considerations for inclusion

1. Staff acquisition


2. Resource Calendars


3. Staff Release Plan


4. Training Needs


5. Recognition and Rewards


6. Compliance


7. Safety

Acquire Project Team process

confirms HR availability and obtains the team necessary to complete project activities.

Acquire Project Team process inputs

1. HR Mgmt Plan


2 & 3. OPA's & EEF's



Acquire Project Team process T&T's

1. Pre-assignment


2. Negotiation


3. Acquisition


4. Virtual Teams


5. Multi-Criteria Decision Analysis

Multi-Criteria Decision Analysis grading categories

1. Availability


2. Cost


3. Experience


4. Ability


5. Knowledge


6. Skills


7. Attitude


8. International Factors

Acquire Project Team process outputs

1. Project Staff Assignments


2. Resource Calendars


3. PM Plan Updates

PM team is responsible for

1. Providing leadership and mgmt throughout


2. Influence the project team


3. Model professional and ethical behavior

Plan HR Mgmt process Data Flow Diagram

a

Resource Calendar provided in the Plan HR Mgmt process is

a histogram and provides info such as when project team members will be needed, when resources will join and leave, and when acquisition activities such as recruiting should begin

Acquire Project Team process Data Flow Diagram

a