• Shuffle
    Toggle On
    Toggle Off
  • Alphabetize
    Toggle On
    Toggle Off
  • Front First
    Toggle On
    Toggle Off
  • Both Sides
    Toggle On
    Toggle Off
  • Read
    Toggle On
    Toggle Off
Reading...
Front

Card Range To Study

through

image

Play button

image

Play button

image

Progress

1/51

Click to flip

Use LEFT and RIGHT arrow keys to navigate between flashcards;

Use UP and DOWN arrow keys to flip the card;

H to show hint;

A reads text to speech;

51 Cards in this Set

  • Front
  • Back
PV
Planned Value
EV
Earned Value
AC
Actual Cost
BAC
Budget at Completion
CV
Cost Variance = (EV - AC)
SV
Schedule Variance = (EV - PV)
CPI
Cost Performance Index;
CPI = (EV/AC)
SPI
Schedule Performance Index = (EV/PV)
EAC
Estimate at Completion = (BAC/CPI)
ETC
Estimate to Complete = (EAC - AC)
VAC
Variance at Completion = (BAC - EAC)
(Activity Duration Estimation)"
An estimating technique that uses the values of parameters, such as scope, cost, budget, and duration from a previous, similar activity for estimating for future activity.
Apportioned Effort (AE)
Effort applied to project work that is not readily divisible into discrete efforts for that work, but which is related in direct proportion to measurable discrete work efforts.
(Activity Sequencing)"
A schedule network diagramming technique in which schedule activities are represented by arrows and nodes represent sequence in which the schedule activities are expected to be performed.
(Risk Identification)"
A technique that explores the accuracy of assumptions and identifies risks to the project from inaccuracy of the assumption.
Backward Pass
The calculation of the late finish and start dates for uncompleted work by working backwards through the schedule logic from the end date.
(Cost Estimating)"
Method of estimating a component of work from the lowest, more detailed pieces of work and then aggregating the resource/cost needs upwards into a total quantity for that component.
(Risk Identification)"
A general data gathering and creativity technique that can be used to identify risks, ideas, or solutions to issues by using a group of team members or experts and recording their ideas.
Budget at Completion
The sum of all the budgets established for the work to be performed on a project. The total PLANNED VALUE for a project.
[Tool]"
Any numbering system used to monitor project costs by category (e.g. labor, supplies). Based upon the corporate chart of accounts of the perfoming organization.
[Tool]"
Any numbering system used to uniquely identify each component of the WBS.
Common Cause
A source of variation on a control chart that would be considered normal and within limits and is predictable.
INPUT of Plan Contracting"
A narrative description of products, services, or results to be supplied under contract.
[Technique]"
A control point placed on the WBS above the Work Package level to be used for planning when associated work packages have not yet been planned.
(Perform Quality Control)"
A graphic display of process data over time and against established control limits. Has a centerline that assists in detecting trends of plotted values towards the limits.
(on a control chart in the Perform Quality Control process)"
The area composed of 3 standard deviations on either side of the centerline or mean of a control chart that reflects the expected variation in the data.
(Quality Planning)"
Determining the costs incurred to ensure quality, whether it is Cost of Conformance (Prevention, appraisal costs) or Cost of Non-Conformance (Failure, rework, waste, reputation)
Cost-Plus-Percent-Cost (CPPC)"
A type of reimbursable contract where the buyer reimburses the seller for the allowable costs for the contract work and the seller also receives a fee calculated as an agreed upon percentage of Actual Cost.
Cost-Plus-Fixed-Fee (CPFF)
A type of reimbursable contract where the buyer reimburses the seller for the allowable costs for the contract work and the seller also receives a fixed amount of profit (Fee).
Cost-Plus-Incentive-Fee (CPIF)
A type of reimbursable contract where the buyer reimburses the seller for the allowable costs for the contract work and the seller earns its profit if it meets defined performance criteria.
Cost-Reimbursable Contract
A type of contract where the buyer reimburses the seller for the allowable costs for the contract work and the seller also receives a fee representing the seller's profit.
CV = BCWP - ACWP"
A measure of cost performance on a project represented by the Earned Value (EV) - Actual Cost (AC)
(Schedule Development)"
A specific type of project schedule compression technique performed by taking action to compress the total schedule duration for the least incremental cost by analyzing cost and schedule tradeoffs.
(Schedule Development)"
A schedule network analysis technique that modifies the project schedule to account for limited resources. (mixes deterministic and probablilistic approaches)
(Schedule Development)"
Generally, but not always, the sequence of schedule activities that determine the duration of the project. The longest path through the project.
(Schedule Development)"
A schedule network analysis method used to determine the amount of scheduling flexibility(amount of float) on various logical network paths to determine the minimum project duration. Forward pass to get early start and finish dates/Backward pass to get late start and finish dates.
(Quantitative Risk Analysis)"
A diagram that describes a decision under consideration and the implications of choosing one or another alternative. Used when future outcomes are uncertain. (Expected monetary value analysis)
(Risk Identification)"
An information gathering technique used as a way to reach a consensus of experts on a subject while reducing bias. (Anonymous participation)
(Quality)"
A management technique used for evaluationg a proposed design to ensure that the design meets customer requirements.
Discrete Effort (opposite of apportioned Effort)
Work efford that is related to the completion of specific WBS components and deliverables that can be accurately planned and measured.
(Cost Control) (Schedule Control) (Monitor and Control Project Work)"
A Management methodology for measuring project performance by determining BCWP (EV) and comparing it to the actual cost (AC) ACWP and project progress by comparing EV/BCWP to Planned Value (PV, BCWS).
(Quantitative Risk Analysis)"
A statistical technique that calculates the average outcome when the future is uncertain commonly used in decision tree analysis.
Firm-Fixed-Price (FFP)
Type of Fixed price contract where the buyer pays the seller a set amount regardless of the seller's costs.
Fixed-Price-Incentive-Fee (FPIF)
A type of contract where the buyer pays the seller a set amount and the seller can earn an additional amount if the seller meets defined criteria.
Fixed-Price or Lump-Sum Contract
Type of contract involving a fixed total price for a well defined product.
(Perform Quality Control)"
The depiction in a diagram format of the inputs, process actions and outputs of one or more processes within a system
Outout to M&CPW"
Estimates or predictions of conditions and events in the projects future based on projects past and expected performance. Updated and reissued based on Work performance info as the project is executed. Yields EAC and ETC
Free Float (FF)
Amount of time that a schedule activity can be delayed without delaying the early start of any immediately following schedule activities.
Grade
A category or rank used to distinguish items that have the same functional use, but do not share the same requirements for quality.
(Contract Admin)"
Examining or measuring to verify whether an activity, component, product, result or service conforms to specified requirements.
(Schedule Development)"
A mod of a logical relationship that allows an acceleration of the succesor activity.