Define Activities
|
Inputs:
1 Scope baseline, 2 Enterprise environmental factors, 3 Organizational process assets; Tools & Techniques: 1 Decomposition, 2 Rolling wave planning, 3 Templates, 4 Expert judgment; Outputs: 1 Activity list, 2 Activity attributes, 3 Milestone list. |
|
Sequence Activities
|
Inputs:
1 Activity list, 2 Activity attributes, 3 Milestone list, 4 Project scope statement, 5 Organizational process assets; Tools & Techniques: 1 Precedence diagramming method (PDM) 2 Dependency determination, 3 Applying leads and lags, 4 Schedule network templates; Outputs: 1 Project schedule network diagrams, 2 Project document updates. |
|
Estimate Activity Resources
|
Inputs:
1 Activity list, 2 Activity attributes, 3 Resource calendars, 4 Enterprise environmental factors, 5 Organizational process assets; Tools & Techniques: 1 Expert judgment, 2 Alternatives analysis, 3 Published estimating data, 4 Bottom-up estimating, 5 Project management software; Outputs: 1 Activity resource requirements, 2 Resource breakdown structure, 3 Project document updates. |
|
Estimate Activty Durations
|
Inputs:
1 Activity list, 2 Activity atributes, 3 Activity resource requirements, 4 Resource calendars, 5 Project scope statement, 6 Enterprise environmental factors, 7 Organizational process assets; Tools & Techniques: 1 Expert judgment, 2 Analogous estimating, 3 Parametric estimating, 4 Three-point estimates, 5 Reserve analysis; Outputs: 1 Activity duration estimates, 2 Projct document updates. |
|
Develop Schedule
|
Inputs:
1 Activity list, 2 Activity attributes, 3 Project schedule netowrk diagrams, 4 Activity resource requirements, 5 Resource calendars, 6 Activity duration estimates, 7 Project scope statement, 8 Enterprise environmental factors, 9 Organizational process assets; Tools & Techniques: 1 Schedule network analysis, 2 Critical path method, 3 Critical chain method, 4 Resource leveling, 5 What-if scenario analysis, 6 Applying leads and lags, 7 Schedule compression, 8 Scheduling tool; Outputs: 1 Project schedule, 2 Schedule baseline, 3 Schedule data, 4 Project document updates. |
|
Control Schedule
|
Inputs:
1 Project management plan, 2 Project schedule, 3 Work performance information, 4 Organizational process assets, Tools & Techniques: 1 Performance reviews, 2 Variance analysis, 3 Project management software, 4 Resource leveling, 5 What-if scenario analysis, 6 Adjusting leads and lags, 7 Schedule compression, 8 Scheduling tool; Outputs: 1 Work performance, 2 Organizational process asseets updates, 3 Change requests, 4 Project management plan updates, 5 Project document updates. |