Select project manager
|
BEFORE:<NOTHING>
AFTER:Determine company culture and existing systems |
|
Determine company culture and existing systems
|
BEFORE:Select project manager
AFTER:Determine processes, procedures and historical information |
|
Determine processes, procedures and historical information
|
BEFORE:Determine company culture and existing systems|AFTER:Divide project into phases
|
|
Divide project into phases
|
BEFORE:Determine processes, procedures and historical information|AFTER:Identify stakeholders
|
|
Identify stakeholders
|
BEFORE:Divide project into phases|AFTER:Document business need
|
|
Document business need
|
BEFORE:Identify stakeholders|AFTER:Determine project objectives
|
|
Determine project objectives
|
BEFORE:Document business need|AFTER:Document constraints and assumptions
|
|
Document constraints and assumptions
|
BEFORE:Determine project objectives|AFTER:Develop project charter
|
|
Develop project charter
|
BEFORE:Document constraints and assumptions|AFTER:Develop preliminary project scope statement
|
|
Develop preliminary project scope statement
|
BEFORE:Develop project charter|AFTER:Determine how you will do planning - part of management plan
|
|
Determine how you will do planning - part of management plan
|
BEFORE:Develop preliminary project scope statement|AFTER:Create project scope statement
|
|
Create project scope statement
|
BEFORE:Determine how you will do planning - part of management plan|AFTER:Determine project team
|
|
Determine project team
|
BEFORE:Create project scope statement|AFTER:Create WBS and WBS dictionary
|
|
Create WBS and WBS dictionary
|
BEFORE:Determine project team|AFTER:Create activity list
|
|
Create activity list
|
BEFORE:Create WBS and WBS dictionary|AFTER:Create network diagram
|
|
Create network diagram
|
BEFORE:Create activity list|AFTER:Estimate resource requirements
|
|
Estimate resource requirements
|
BEFORE:Create network diagram|AFTER:Estimate time and cost
|
|
Estimate time and cost
|
BEFORE:Estimate resource requirements|AFTER:Determine critical path
|
|
Determine critical path
|
BEFORE:Estimate time and cost|AFTER:Develop schedule
|
|
Develop schedule
|
BEFORE:Determine critical path|AFTER:Develop budget
|
|
Develop budget
|
BEFORE:Develop schedule|AFTER:Determine quality standards, processes and performance metrics
|
|
Determine quality standards, processes and performance metrics
|
BEFORE:Develop budget|AFTER:Determine roles and responsibilities
|
|
Determine roles and responsibilities
|
BEFORE:Determine quality standards, processes and performance metrics|AFTER:Determine communication requirements
|
|
Determine communication requirements
|
BEFORE:Determine roles and responsibilities|AFTER:Identify risks, qualitative and quantitative risk analysis and response planning
|
|
Identify risks, qualitative and quantitative risk analysis and response planning
|
BEFORE:Determine communication requirements|AFTER:Iterations - go back
|
|
Iterations - go back
|
BEFORE:Identify risks, qualitative and quantitative risk analysis and response planning|AFTER:Determine what to purchase
|
|
Determine what to purchase
|
BEFORE:Iterations - go back|AFTER:Prepare procurement documents
|
|
Prepare procurement documents
|
BEFORE:Determine what to purchase|AFTER:Finalize "how to execute and control" aspects of all management plans
|
|
Finalize "how to execute and control" aspects of all management plans
|
BEFORE:Prepare procurement documents|AFTER:Develop a process improvement plan
|
|
Develop a process improvement plan
|
BEFORE:Finalize "how to execute and control" aspects of all management plans|AFTER:Develop finalize project management plan and perfomance measurement baseline
|
|
Develop final project management plan and perfomance measurement baseline
|
BEFORE:Develop a process improvement plan|AFTER:Gain formal approval
|
|
Gain formal approval
|
BEFORE:Develop final project management plan and perfomance measurement baseline
AFTER:Hold kickoff meeting |
|
Hold kickoff meeting
|
BEFORE:Gain formal approval|AFTER:Acquire final team
|
|
Acquire final team
|
BEFORE:Hold kickoff meeting|AFTER:Execute the project managemlent plan
|
|
Execute the project managemlent plan
|
BEFORE:Acquire final team|AFTER:Complete product scope
|
|
Complete product scope
|
BEFORE:Execute the project managemlent plan|AFTER:Recommend changes and corrective actions
|
|
Recommend changes and corrective actions
|
BEFORE:Complete product scope
AFTER:Send and receive information |
|
Send and receive information
|
BEFORE:Recommend changes and corrective actions|AFTER:Implement approved changes, defect fixes, preventive and corrective actions
|
|
Implement approved changes, defect fixes, preventive and corrective actions
|
BEFORE:Send and receive information|AFTER:Continuous improvement
|
|
Continuous improvement
|
BEFORE:Implement approved changes, defect fixes, preventive and corrective actions|AFTER:Follow the processes
|
|
Follow the processes
|
BEFORE:Continuous improvement|AFTER:Team building
|
|
Team building
|
BEFORE:Follow the processes|AFTER:Give rewards and recognition
|
|
Give rewards and recognition
|
BEFORE:Team building|AFTER:Hold progress meetings
|
|
Hold progress meetings
|
BEFORE:Give rewards and recognition|AFTER:Use work authorization system
|
|
Use work authorization system
|
BEFORE:Hold progress meetings|AFTER:Request seller response
|
|
Request seller response
|
BEFORE:Use work authorization system|AFTER:Select the seller
|
|
Select the seller
|
BEFORE:Request seller response|AFTER:Measure against the perfomance measurement baselines
|
|
Measure against the perfomance measurement baselines
|
BEFORE:Select the seller|AFTER:Measure according to management plans
|
|
Measure according to management plans
|
BEFORE:Measure against the perfomance measurement baselines|AFTER:Determine variances and if the warrant for corrective action
|
|
Determine variances and if the warrant for corrective action
|
BEFORE:Measure according to management plans|AFTER:Scope Verification
|
|
Scope Verification
|
BEFORE:Determine variances and if the warrant for corrective action|AFTER:Configuration management
|
|
Configuration management
|
BEFORE:Scope Verification|AFTER:Recommend changes, defect fixes, preventive and corrective actions
|
|
Recommend changes, defect fixes, preventive and corrective actions
|
BEFORE:Configuration management|AFTER:Integrated change control
|
|
Integrated change control
|
BEFORE:Recommend changes, defect fixes, preventive and corrective actions|AFTER:Implement approved changes, defect fixes, preventive and corrective actions
|
|
Approve changes, defect repair, preventive and corrective actions
|
BEFORE:Integrated change control|AFTER:Risk audits
|
|
Risk audits
|
BEFORE:Approve changes, defect fixes, preventive and corrective actions|AFTER:Manage reserves
|
|
Manage reserves
|
BEFORE:Risk audits|AFTER:Use issue logs
|
|
Use issue logs
|
BEFORE:Manage reserves|AFTER:Facilitate conflict resolution
|
|
Facilitate conflict resolution
|
BEFORE:Use issue logs|AFTER:Individual team member perfomance
|
|
Individual team member perfomance
|
BEFORE:Facilitate conflict resolution|AFTER:Performance reporting
|
|
Performance reporting
|
BEFORE:Individual team member perfomance|AFTER:Use forecasts
|
|
Use forecasts
|
BEFORE:Performance reporting|AFTER:Administer contracts
|
|
Administer contracts
|
BEFORE:Use forecasts|AFTER:Develop closure procedures
|
|
Develop closure procedures
|
BEFORE:Administer contracts|AFTER:Complete contract closure
|
|
Complete contract closure
|
BEFORE:Develop closure procedures|AFTER:Confirm work is done to requirements
|
|
Confirm work is done to requirements
|
BEFORE:Complete contract closure|AFTER:Gain formal acceptance of the product
|
|
Gain formal acceptance of the product
|
BEFORE:Confirm work is done to requirements|AFTER:Final perfomance reporting
|
|
Final perfomance reporting
|
BEFORE:Gain formal acceptance of the product|AFTER:Index and archive records
|
|
Index and archive records
|
BEFORE:Final perfomance reporting|AFTER:Update lessons learned knowledge base
|
|
Update lessons learned knowledge base
|
BEFORE:Index and archive records|AFTER:Hand off completed product
|
|
Hand off completed product
|
BEFORE:Update lessons learned knowledge base|AFTER:Release resources
|
|
Release resources
|
BEFORE:Hand off completed product|AFTER:<END>
|